149-151 S WESTGATE AVE 90049

Certificate Information: 149-151 S WESTGATE AVE 90049

Application / Permit
22010-20000-05165
Plan Check / Job No.
B22VN15680
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (47'-4"x75'-0"), 3301 SQFT SINGLE FAMILY DWELLING AND ATTACHED 2 CAR GARAGE (384 SQFT) W/ BASEMENT 2468 SQFT AND ATTACHED ADU (297 SQFT) PER LAMC 12.22 A.33(c) AND (e) W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 2/17/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 PETER MOSESIAN
Corrections Issued 11/2/2022 PETER MOSESIAN
Quality Review Completed 11/8/2022 OMID HEDAYAT
Building Plans Picked Up 11/9/2022 APPLICANT
Plan Check Approved 2/2/2023 PETER MOSESIAN
Issued 2/17/2023 APPLICANT
CofO in Progress 11/8/2024 KENNETH NAGLE
Permit Finaled 11/12/2024 RICHARD STEINBACH
CofO Issued 11/12/2024 RICHARD STEINBACH
Permit Finaled 11/12/2024 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development Cleared 12/7/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 12/10/2022 ERIK BEASLEY
ZA Case Cleared 12/13/2022 DANG NGUYEN
Address approval Cleared 12/17/2022 AHMED AMARRAGY
Eng Process Fee Ord 176,300 Cleared 12/27/2022 AHMED AMARRAGY
Sewer availability Cleared 12/27/2022 AHMED AMARRAGY
Hydrant and Access approval Cleared 1/16/2023 GILBERT URREA
Specific Plan Cleared 1/19/2023 FREDDY GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/22/2023 Partial Inspection KEVIN SARGSYAN
PLUMBING-Rough 4/19/2023 Conditional Approval STEPHANIE SWANSON
PLUMBING-Rough 5/1/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Deputy Reinf. Concrete 5/12/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/12/2023 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 5/16/2023 No Access for Inspection KEVIN SARGSYAN
Deputy Reinf. Concrete 6/2/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Shotcrete 6/15/2023 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 6/15/2023 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 6/15/2023 Partial Approval CARLOS MATAMOROS
Deputy Shotcrete 6/16/2023 No Access for Inspection KENNETH NAGLE
Deputy Shotcrete 6/20/2023 Conditional Approval MICHAEL PELHAM
Sewer 7/31/2023 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 8/8/2023 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 8/10/2023 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 8/11/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 8/16/2023 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Partial Approval KEVIN SARGSYAN
HVAC-Rough 10/3/2023 Approved OGANES TARAKHCHYAN
Deputy Wood Construction 10/11/2023 No Access for Inspection KENNETH NAGLE
Deputy Wood Construction 10/11/2023 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 10/31/2023 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 11/2/2023 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 11/9/2023 Partial Approval ARAM AVEDISIAN
Special/Order Compliance 11/9/2023 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Partial Approval BRENDAN LOONEY
Green Building Rough 11/13/2023 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 11/13/2023 Approved BRENDAN LOONEY
Interior/Exterior Lathing 11/22/2023 Partial Approval CARLOS MATAMOROS
Pre-Inspection 11/27/2023 Partial Inspection DANIEL ORRANTE
Pre-Inspection 11/30/2023 Corrections Issued STEPHANIE SWANSON
Special/Order Compliance 12/1/2023 Partial Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 12/14/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 12/14/2023 Approved ARAM AVEDISIAN
Green Building Rough 12/14/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/14/2023 Approved ARAM AVEDISIAN
Insulation 1/16/2024 Approved CHRISTOPHER WILSON
Shower Pan 1/18/2024 Approved KATHRYN BUTTERWORTH
Drywall Nailing 1/22/2024 Approved KENNETH NAGLE
Interior/Exterior Lathing 1/29/2024 Approved CARLOS MATAMOROS
Underground Mechanical 6/5/2024 Partial Approval ARAM AVEDISIAN
HVAC-Final 10/10/2024 Approved CARLOS MATAMOROS
PLUMBING-Final 10/10/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Final 10/15/2024 Approved JESUS RODRIGUEZ
Final 10/15/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 10/15/2024 Approved JESUS RODRIGUEZ
Green Building Final 10/15/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 10/15/2024 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 10/15/2024 Approved JESUS RODRIGUEZ
Smoke Detectors 10/15/2024 Approved JESUS RODRIGUEZ
Final 11/8/2024 OK to Issue CofO KENNETH NAGLE