9762 N CEDROS AVE 91402

Certificate Information: 9762 N CEDROS AVE 91402

Application / Permit
22010-20000-05147
Plan Check / Job No.
B22VN15653
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d)
Permit Issued
Issued on 3/14/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 SELLA BENYAMIN
Corrections Issued 11/17/2022 NILOOFAR MEHRAIN
Quality Review Completed 11/30/2022 STEVEN KIM
Building Plans Picked Up 12/2/2022 APPLICANT
Applicant returned to address corrections 1/10/2023 NILOOFAR MEHRAIN
Plan Check Approved 2/14/2023 NILOOFAR MEHRAIN
Issued 3/14/2023 APPLICANT
CofO in Progress 1/15/2026 JENNIFER RABUCHIN
Permit Finaled 2/2/2026 RUBEN SALAS
CofO Issued 2/2/2026 RUBEN SALAS
Permit Finaled 2/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/5/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 12/5/2022 COLIN LOREDO
Sewer availability Cleared 12/5/2022 COLIN LOREDO
Low Impact Development Cleared 12/16/2022 CHRIS VONG
Hydrant and Access approval Cleared 12/19/2022 KURT CORRAL
Roof/Waste drainage to street Cleared 12/20/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/2/2025 Partial Approval JENNIFER RABUCHIN
Sewer 9/23/2025 Approved JENNIFER RABUCHIN
Underground Mechanical 9/23/2025 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 9/26/2025 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 9/26/2025 Approved JENNIFER RABUCHIN
METHANE-Barrier 9/26/2025 Approved JENNIFER RABUCHIN
METHANE-Subgrade 9/26/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/17/2025 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 10/23/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 10/23/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/27/2025 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 10/27/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/6/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 11/6/2025 Approved JENNIFER RABUCHIN
Green Building Rough 11/6/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/6/2025 Partial Approval JENNIFER RABUCHIN
Insulation 11/13/2025 Approved CHRISTOPHER MORFIN
Shower Pan 11/13/2025 Approved CHRISTOPHER MORFIN
Drywall Nailing 11/21/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/3/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 12/10/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 12/10/2025 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 12/12/2025 Approved JENNIFER RABUCHIN
Service/Power Release 12/12/2025 Partial Inspection JENNIFER RABUCHIN
Final 12/30/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 12/30/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/9/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 1/9/2026 Not Ready for Inspection JENNIFER RABUCHIN
Final 1/9/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/9/2026 Approved JENNIFER RABUCHIN
HVAC-Final 1/9/2026 Approved JENNIFER RABUCHIN
METHANE-Final 1/9/2026 Approved JENNIFER RABUCHIN
METHANE-Rough 1/9/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/9/2026 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 1/9/2026 Approved JENNIFER RABUCHIN
Smoke Detectors 1/9/2026 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 1/9/2026 Approved JENNIFER RABUCHIN
Final 1/14/2026 OK to Issue CofO JENNIFER RABUCHIN