4181 N LANAI ROAD 91436

Certificate Information: 4181 N LANAI ROAD 91436

Application / Permit
22010-20000-05138
Plan Check / Job No.
B22VN15620
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1-STORY (197'-0"x64'-6"), 3415 SQFT SINGLE FAMILY DWELLING, W/(5949 SQFT) HABITABLE BASEMENT AND (1595 SQFT) ATTACHED COVERED PATIO, (808 SQFT) 3 CAR GARAGE W/NFPA 13R SPRINKLERS THROUGHOUT
Permit Issued
Issued on 6/21/2024
Issuing Office
Valley
Current Status
Issued on 6/21/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/19/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 PETER MOSESIAN
Corrections Issued 10/29/2022 PETER MOSESIAN
Quality Review Completed 11/2/2022 OMID HEDAYAT
Building Plans Picked Up 11/9/2022 APPLICANT
Plan Check Approved 6/11/2024 PETER MOSESIAN
Issued 6/21/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/20/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/20/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/20/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/20/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/20/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/20/2022 LEE GUILBEAUX
Miscellaneous Cleared 12/20/2022 LEE GUILBEAUX
Street Frontage Cleared 12/20/2022 LEE GUILBEAUX
Sewer availability Cleared 12/21/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/10/2023 LEE GUILBEAUX
Hydrant and Access approval Cleared 1/18/2023 KURT CORRAL
Private street Cleared 3/8/2023 NOAH MCCOY
ZA Case Cleared 3/8/2023 NOAH MCCOY
Low Impact Development Cleared 7/11/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 7/11/2023 RYAN KIM
Disturb/Remove Protected Trees Cleared 8/15/2023 ADALBERTO VERA
Certificate of Compliance Cleared 9/13/2023 MARC WOERSCHING

Contact Information

Contractor Owner-Builder       ,
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 347 ROBERTSON BLVD      BEVERLY HILLS, CA 90211
Engineer Markov,, George P; Lic. No.: C55855 1623 THOMPSON AVE      GLENDALE, CA 91201
Engineer Nazari,, Arthur; Lic. No.: C53497 23300 POMPANO STREET      MALIBU, CA 90265
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/1/2024 Approved THOMAS FINNILA
Footing/Foundation/Slab 8/7/2024 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 8/14/2024 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 8/19/2024 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 8/23/2024 Corrections Issued THOMAS FINNILA
Piling/Pier/Caisson 8/26/2024 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 9/12/2024 Partial Inspection THOMAS FINNILA
Footing/Foundation/Slab 10/28/2024 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 11/7/2024 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 11/15/2024 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 11/22/2024 Partial Approval THOMAS FINNILA
Deputy Reinf. Concrete 11/26/2024 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 12/3/2024 Conditional Approval THOMAS FINNILA
Deputy Shotcrete 12/9/2024 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 12/16/2024 Partial Approval SEAN WIRCH
PLUMBING-Rough 2/24/2025 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 3/5/2025 Not Ready for Inspection THOMAS FINNILA
Piling/Pier/Caisson 3/7/2025 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 3/13/2025 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 3/17/2025 Conditional Approval THOMAS FINNILA
Deputy Shotcrete 3/21/2025 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 3/24/2025 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 4/21/2025 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 4/24/2025 Partial Approval THOMAS FINNILA
PLUMBING-Rough 5/2/2025 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 5/6/2025 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 5/6/2025 Partial Approval THOMAS FINNILA
Verify Sprinkler Sign Off 5/6/2025 Not Ready for Inspection THOMAS FINNILA
Deputy Reinf. Concrete 5/7/2025 Conditional Approval SEAN WIRCH
Footing/Foundation/Slab 5/15/2025 Corrections Issued JOHN COLEMAN
Deputy Drilled-In Anchors 5/16/2025 Conditional Approval THOMAS FINNILA
Pre-Inspection 5/16/2025 Approved JOHN COLEMAN
Deputy Reinf. Concrete 5/19/2025 Partial Approval SEAN WIRCH
Deputy Wood Construction 6/25/2025 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Conditional Approval THOMAS FINNILA
Shower Pan 8/19/2025 Approved SCOTT SOBEL
PLUMBING-Rough 8/20/2025 Corrections Issued SCOTT SOBEL
Floor/Roof Diaphrgm/Shear Wall 9/9/2025 Partial Approval SEAN WIRCH
Deputy Wood Construction 9/10/2025 Conditional Approval THOMAS FINNILA
Deputy Steel/Welding 9/11/2025 Partial Approval THOMAS FINNILA
HVAC-Rough 9/29/2025 Corrections Issued THOMAS FINNILA
HVAC-Rough 10/10/2025 Approved THOMAS FINNILA
PLUMBING-Rough 10/10/2025 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 11/14/2025 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 12/3/2025 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 12/11/2025 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 12/15/2025 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 12/15/2025 Corrections Issued THOMAS FINNILA
Deputy Wood Construction 12/16/2025 Partial Approval SEAN WIRCH
ELECTRICAL-Rough 12/17/2025 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Partial Approval SEAN WIRCH
Interior/Exterior Lathing 1/14/2026 Partial Approval MORRIS JACKSON
BUILDING-Rough-Frame 1/21/2026 Corrections Issued THOMAS FINNILA
Green Building Rough 1/21/2026 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 1/21/2026 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 1/28/2026 Approved SEAN WIRCH
Green Building Rough 1/28/2026 Approved SEAN WIRCH
PLUMBING-Rough 1/28/2026 Approved SEAN WIRCH
Verify Sprinkler Sign Off 1/28/2026 Approved SEAN WIRCH
Interior/Exterior Lathing 2/9/2026 Partial Approval JOHN KIDWELL
Insulation 2/27/2026 Approved THOMAS FINNILA
Drywall Nailing 3/10/2026 Approved ALEXANDER HANDY