12119 W MAXWELLTON ROAD 91604
Certificate Information: 12119 W MAXWELLTON ROAD 91604
- Application / Permit
- 22010-20000-05132
- Plan Check / Job No.
- B22VN15612
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED (42'-0"x21'-6"), 797 SQFT ADU W/NFPA 13D SPRINKLERS THROUGHOUT PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g)
- Permit Issued
- Issued on 3/2/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | PETER MOSESIAN |
| Corrections Issued | 10/26/2022 | PETER MOSESIAN |
| Quality Review Completed | 10/27/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 10/28/2022 | APPLICANT |
| Applicant returned to address corrections | 2/14/2023 | PETER MOSESIAN |
| Plan Check Approved | 3/2/2023 | PETER MOSESIAN |
| Issued | 3/2/2023 | APPLICANT |
| CofO in Progress | 2/16/2024 | CHRISTOPHE COCHRAN |
| Permit Finaled | 3/18/2024 | RUBEN SALAS |
| CofO Issued | 3/18/2024 | RUBEN SALAS |
| Permit Finaled | 3/18/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/23/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 11/23/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 11/23/2022 | DAGOVERTO GUERRERO |
| Street Frontage | Cleared | 11/23/2022 | DAGOVERTO GUERRERO |
| ZI | Cleared | 12/12/2022 | BRENNEN OBETO |
| Low Impact Development | Cleared | 12/14/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 12/15/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 2/22/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/24/2023 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 4/25/2023 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 4/28/2023 | Approved | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2023 | Approved | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 6/16/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2023 | Approved | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 6/22/2023 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 6/23/2023 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 6/26/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Rough | 6/26/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/26/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Shower Pan | 6/26/2023 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 6/26/2023 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 6/30/2023 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 6/30/2023 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 7/14/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 7/26/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/2/2023 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Final | 12/14/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 1/22/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Final | 1/22/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 1/22/2024 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 1/26/2024 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Final | 1/26/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 1/26/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 2/14/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Final | 2/14/2024 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 2/14/2024 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 2/14/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 2/14/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 2/16/2024 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 2/16/2024 | Approved | CHRISTOPHE COCHRAN |