4603 N BALBOA BLVD 91316

Certificate Information: 4603 N BALBOA BLVD 91316

Application / Permit
22010-20000-05126
Plan Check / Job No.
B22VN15606
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 53'6" X 16'6" ONE STORY DETACHED ACCESSORY DWELLING UNIT AS PER CA GOV CODE 65852.2(E)(1)(B) , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/9/2023
Issuing Office
Current Status
Issued on 11/9/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/19/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 RARES BODEA
Corrections Issued 11/1/2022 RARES BODEA
Quality Review Completed 11/4/2022 STEVEN KIM
Building Plans Picked Up 11/9/2022 APPLICANT
Applicant returned to address corrections 1/30/2023 RARES BODEA
Applicant returned to address corrections 2/23/2023 RARES BODEA
Applicant returned to address corrections 5/12/2023 RARES BODEA
Applicant returned to address corrections 5/15/2023 RARES BODEA
Applicant returned to address corrections 5/22/2023 RARES BODEA
Applicant returned to address corrections 6/1/2023 RARES BODEA
Applicant returned to address corrections 8/14/2023 RARES BODEA
Applicant returned to address corrections 9/6/2023 RARES BODEA
Plan Check Approved 9/7/2023 RARES BODEA
Issued 11/9/2023 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/19/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/19/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/19/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/19/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/19/2022 LEE GUILBEAUX
Street Frontage Cleared 12/19/2022 LEE GUILBEAUX
Address approval Cleared 12/21/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/21/2022 LEE GUILBEAUX
Tract Map conditions Cleared 1/10/2023 BRENNEN OBETO
Tract Map conditions Cleared 1/10/2023 BRENNEN OBETO
Private street Cleared 3/6/2023 BRENNEN OBETO
Tract Map conditions Cleared 3/6/2023 BRENNEN OBETO
Sewer availability Cleared 3/13/2023 LEE GUILBEAUX
Distance to fire station Cleared 4/26/2023 MATTHEW CRAIG
Hydrant and Access approval Cleared 4/26/2023 MATTHEW CRAIG
Low Impact Development Cleared 5/23/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/24/2023 LEE GUILBEAUX
GPI Written Notices Cleared 6/1/2023 RARES BODEA
Grading Pre-Inspection Cleared 6/1/2023 RARES BODEA

Contact Information

Contractor E T Development Inc; Lic. No.: 994749-B 7256 BELLAIRE AVENUE      NORTH HOLLYWOOD, CA 91605
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/7/2024 Corrections Issued THOMAS FINNILA
Special/Order Compliance 10/18/2024 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 10/29/2024 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 11/21/2024 Partial Approval THOMAS FINNILA
PLUMBING-Rough 12/10/2024 Partial Approval THOMAS FINNILA
PLUMBING-Rough 12/11/2024 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/17/2024 Partial Approval THOMAS FINNILA
Deputy Wood Construction 2/4/2025 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 2/10/2025 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 2/10/2025 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/24/2025 Partial Approval THOMAS FINNILA
Shower Pan 3/5/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 Not Ready for Inspection THOMAS FINNILA
Special/Order Compliance 3/17/2025 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 3/25/2025 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 3/25/2025 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 4/3/2025 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 4/3/2025 Approved THOMAS FINNILA
Interior/Exterior Lathing 4/3/2025 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 4/9/2025 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 4/9/2025 Not Ready for Inspection THOMAS FINNILA
Special/Order Compliance 4/11/2025 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 4/16/2025 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 4/24/2025 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 4/24/2025 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 4/24/2025 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 5/1/2025 Conditional Approval JOHN COLEMAN
ELECTRICAL-Rough 5/1/2025 Approved JOHN COLEMAN
Green Building Rough 5/1/2025 Corrections Issued JOHN COLEMAN
Verify Sprinkler Sign Off 5/1/2025 Approved JOHN COLEMAN
BUILDING-Rough-Frame 5/6/2025 Conditional Approval THOMAS FINNILA
Rough-Elec/Plmb/HVAC 5/6/2025 Approved THOMAS FINNILA
Insulation 5/13/2025 Approved THOMAS FINNILA
Interior/Exterior Lathing 5/13/2025 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 5/19/2025 Partial Approval DAVID SCANTLIN
Interior/Exterior Lathing 5/19/2025 Partial Approval DAVID SCANTLIN
Special/Order Compliance 5/19/2025 Not Ready for Inspection DAVID SCANTLIN
Underground Mechanical 6/2/2025 Not Ready for Inspection THOMAS FINNILA
Sewer 6/3/2025 Approved THOMAS FINNILA
Underground Mechanical 6/6/2025 Not Ready for Inspection THOMAS FINNILA
Gas Test 6/9/2025 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 6/10/2025 Not Ready for Inspection THOMAS FINNILA