4603 N BALBOA BLVD 91316
Certificate Information: 4603 N BALBOA BLVD 91316
- Application / Permit
- 22010-20000-05126
- Plan Check / Job No.
- B22VN15606
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 53'6" X 16'6" ONE STORY DETACHED ACCESSORY DWELLING UNIT AS PER CA GOV CODE 65852.2(E)(1)(B) , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/9/2023
- Issuing Office
- Current Status
- Issued on 11/9/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | RARES BODEA |
| Corrections Issued | 11/1/2022 | RARES BODEA |
| Quality Review Completed | 11/4/2022 | STEVEN KIM |
| Building Plans Picked Up | 11/9/2022 | APPLICANT |
| Applicant returned to address corrections | 1/30/2023 | RARES BODEA |
| Applicant returned to address corrections | 2/23/2023 | RARES BODEA |
| Applicant returned to address corrections | 5/12/2023 | RARES BODEA |
| Applicant returned to address corrections | 5/15/2023 | RARES BODEA |
| Applicant returned to address corrections | 5/22/2023 | RARES BODEA |
| Applicant returned to address corrections | 6/1/2023 | RARES BODEA |
| Applicant returned to address corrections | 8/14/2023 | RARES BODEA |
| Applicant returned to address corrections | 9/6/2023 | RARES BODEA |
| Plan Check Approved | 9/7/2023 | RARES BODEA |
| Issued | 11/9/2023 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/19/2022 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 12/19/2022 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 12/19/2022 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 12/19/2022 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 12/19/2022 | LEE GUILBEAUX |
| Street Frontage | Cleared | 12/19/2022 | LEE GUILBEAUX |
| Address approval | Cleared | 12/21/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2022 | LEE GUILBEAUX |
| Tract Map conditions | Cleared | 1/10/2023 | BRENNEN OBETO |
| Tract Map conditions | Cleared | 1/10/2023 | BRENNEN OBETO |
| Private street | Cleared | 3/6/2023 | BRENNEN OBETO |
| Tract Map conditions | Cleared | 3/6/2023 | BRENNEN OBETO |
| Sewer availability | Cleared | 3/13/2023 | LEE GUILBEAUX |
| Distance to fire station | Cleared | 4/26/2023 | MATTHEW CRAIG |
| Hydrant and Access approval | Cleared | 4/26/2023 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 5/23/2023 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/24/2023 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 6/1/2023 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 6/1/2023 | RARES BODEA |
Contact Information
| Contractor | E T Development Inc; Lic. No.: 994749-B | 7256 BELLAIRE AVENUE NORTH HOLLYWOOD, CA 91605 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/7/2024 | Corrections Issued | THOMAS FINNILA |
| Special/Order Compliance | 10/18/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 10/29/2024 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 11/21/2024 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 12/10/2024 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 12/11/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2024 | Partial Approval | THOMAS FINNILA |
| Deputy Wood Construction | 2/4/2025 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 2/10/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Partial Approval | THOMAS FINNILA |
| Shower Pan | 3/5/2025 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Special/Order Compliance | 3/17/2025 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 3/25/2025 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 3/25/2025 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 4/3/2025 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 4/3/2025 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 4/3/2025 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 4/9/2025 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 4/9/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Special/Order Compliance | 4/11/2025 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 4/16/2025 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 4/24/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 4/24/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 4/24/2025 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 5/1/2025 | Conditional Approval | JOHN COLEMAN |
| ELECTRICAL-Rough | 5/1/2025 | Approved | JOHN COLEMAN |
| Green Building Rough | 5/1/2025 | Corrections Issued | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 5/1/2025 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 5/6/2025 | Conditional Approval | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 5/6/2025 | Approved | THOMAS FINNILA |
| Insulation | 5/13/2025 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 5/13/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Drywall Nailing | 5/19/2025 | Partial Approval | DAVID SCANTLIN |
| Interior/Exterior Lathing | 5/19/2025 | Partial Approval | DAVID SCANTLIN |
| Special/Order Compliance | 5/19/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Underground Mechanical | 6/2/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Sewer | 6/3/2025 | Approved | THOMAS FINNILA |
| Underground Mechanical | 6/6/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Gas Test | 6/9/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Underground Mechanical | 6/10/2025 | Not Ready for Inspection | THOMAS FINNILA |