13318 W CORCORAN ST 91340

Certificate Information: 13318 W CORCORAN ST 91340

Application / Permit
22010-20000-05120
Plan Check / Job No.
B22VN15599
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20' X 30' TWO STORY ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33(C) AND (D), ALL WORK PER ENGiNEERING
Permit Issued
Issued on 2/3/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 RARES BODEA
Corrections Issued 11/21/2022 RARES BODEA
Quality Review Completed 12/6/2022 STEVEN KIM
Building Plans Picked Up 12/7/2022 APPLICANT
Plan Check Approved 1/30/2023 RARES BODEA
Issued 2/3/2023 APPLICANT
CofO in Progress 4/2/2025 MICHEL ABAJAN
Permit Finaled 4/15/2025 RUBEN SALAS
CofO Issued 4/15/2025 RUBEN SALAS
Permit Finaled 4/15/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/12/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/21/2022 CARLOS AGUILERA
Sewer availability Cleared 12/21/2022 CARLOS AGUILERA
Low Impact Development Cleared 1/19/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 1/19/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/12/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 4/12/2023 Conditional Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 4/19/2023 Approved MICHEL ABAJAN
Footing/Foundation/Slab 4/19/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 6/13/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/13/2023 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 6/13/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/30/2023 Corrections Issued MICHEL ABAJAN
Green Building Rough 6/30/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 6/30/2023 Corrections Issued MICHEL ABAJAN
Verify Sprinkler Sign Off 6/30/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 7/11/2023 Approved MICHEL ABAJAN
Green Building Rough 7/11/2023 Approved MICHEL ABAJAN
HVAC-Rough 7/11/2023 Approved MICHEL ABAJAN
Insulation 7/21/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/21/2023 Approved MICHEL ABAJAN
Drywall Nailing 8/7/2023 Approved MICHEL ABAJAN
Gas Test 8/21/2023 No Access for Inspection MICHEL ABAJAN
Shower Pan 8/21/2023 No Access for Inspection MICHEL ABAJAN
Gas Test 8/23/2023 Approved MICHEL ABAJAN
Shower Pan 8/23/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 9/13/2023 Approved MICHEL ABAJAN
Underground Mechanical 3/29/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/21/2025 Not Ready for Inspection MICHEL ABAJAN
Final 1/21/2025 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 1/21/2025 Approved MICHEL ABAJAN
HVAC-Final 1/21/2025 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Final 1/21/2025 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/21/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 1/21/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 3/6/2025 Approved MICHEL ABAJAN
Final 3/6/2025 Corrections Issued MICHEL ABAJAN
HVAC-Final 3/6/2025 Approved MICHEL ABAJAN
PLUMBING-Final 3/6/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/2/2025 Approved MICHEL ABAJAN
Final 4/2/2025 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 4/2/2025 Approved MICHEL ABAJAN
PLUMBING-Final 4/2/2025 Approved MICHEL ABAJAN
Service/Power Release 4/2/2025 Approved MICHEL ABAJAN