15220 W WILLARD ST 91402

Certificate Information: 15220 W WILLARD ST 91402

Application / Permit
22010-20000-05101
Plan Check / Job No.
B22VN15532
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 48' X 25' ONE-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d). WORK TO BE DONE PER WFPP.
Permit Issued
Issued on 10/18/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2022 APPLICANT
Assigned to Plan Check Engineer 10/21/2022 RAMA DABADGE
Corrections Issued 10/24/2022 RAMA DABADGE
Building Plans Picked Up 10/26/2022 APPLICANT
Applicant returned to address corrections 7/13/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 7/27/2023 SARKIS HARABEDIAN
Applicant returned to address corrections 8/1/2023 RAMA DABADGE
Plan Check Approved 8/1/2023 RAMA DABADGE
No Progress 8/1/2023 RAMA DABADGE
Plan Check Approved 8/8/2023 MADISON ODELL
Issued 10/18/2023 APPLICANT
CofO in Progress 2/9/2025 VINCENT HANLEY
Permit Finaled 2/18/2025 RUBEN SALAS
CofO Issued 2/18/2025 RUBEN SALAS
Permit Finaled 2/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/24/2023 CINDY QI
Eng Process Fee Ord 176,300 Cleared 1/26/2023 CINDY QI
Sewer availability Cleared 1/26/2023 CINDY QI
Low Impact Development Cleared 2/27/2023 ERNEST TSE
Construction near power lines Cleared 5/25/2023 RIDWAN HARDY
Roof/Waste drainage to street Cleared 8/1/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/24/2023 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 10/30/2023 Not Ready for Inspection GREGG CUMMINGS
Footing/Foundation/Slab 11/3/2023 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 11/3/2023 Partial Approval GREGG CUMMINGS
Footing/Foundation/Slab 11/13/2023 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 11/17/2023 Approved GREGG CUMMINGS
Footing/Foundation/Slab 11/17/2023 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 12/13/2023 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 12/13/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 12/13/2023 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 12/26/2023 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 1/5/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 1/8/2024 Corrections Issued GREGG CUMMINGS
HVAC-Rough 1/8/2024 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 1/8/2024 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 1/11/2024 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 1/11/2024 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 1/11/2024 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 2/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 2/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Pre-Inspection 2/12/2024 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 2/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 3/6/2024 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/11/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 3/11/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 3/11/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 3/11/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 3/11/2024 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 3/11/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/18/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 3/18/2024 Approved CHRISTOPHER ROJAS
Insulation 3/26/2024 Approved KIRK SANDERS
Drywall Nailing 4/1/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/1/2024 Partial Approval MATTHEW NELSON
Interior/Exterior Lathing 4/23/2024 Approved KIRK SANDERS
Shower Pan 4/23/2024 Approved KIRK SANDERS
Sewer 7/3/2024 Approved VINCENT HANLEY
Underground Mechanical 7/3/2024 Approved VINCENT HANLEY
Final 11/5/2024 Corrections Issued VINCENT HANLEY
Green Building Final 11/5/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 11/5/2024 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 11/5/2024 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 11/5/2024 Approved VINCENT HANLEY
Pre-Inspection 1/7/2025 Corrections Issued VINCENT HANLEY
Final 1/24/2025 Not Ready for Inspection VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Approved VINCENT HANLEY
Service/Power Release 1/24/2025 Corrections Issued VINCENT HANLEY
ELECTRICAL-Final 2/6/2025 Approved VINCENT HANLEY
Final 2/6/2025 OK to Issue CofO VINCENT HANLEY
HVAC-Final 2/6/2025 Approved VINCENT HANLEY
PLUMBING-Final 2/6/2025 Approved VINCENT HANLEY
Service/Power Release 2/6/2025 Approved VINCENT HANLEY