819-821 W 57TH ST 90037
Certificate Information: 819-821 W 57TH ST 90037
- Application / Permit
- 22010-20000-05096
- Plan Check / Job No.
- B22VN15525
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan: NEW 2-STORY DUPLEX & ATTACHED 3-CAR GARAGE
- Permit Issued
- Issued on 5/16/2023
- Issuing Office
- Current Status
- CofO Issued on 11/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 10/22/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 10/25/2022 | GARO TELMI |
| Plan Check Approved | 12/20/2022 | ARSALAN SHABESTARI |
| Issued | 5/16/2023 | APPLICANT |
| CofO in Progress | 11/14/2023 | SABAS ALONSO |
| Permit Finaled | 11/26/2023 | DEROLD HAUFF |
| CofO Issued | 11/26/2023 | DEROLD HAUFF |
| Permit Finaled | 11/26/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 11/1/2022 | SHASHA YU |
| Address approval | Cleared | 11/4/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 11/13/2022 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 11/28/2022 | STEVE MELGAR |
| Low Impact Development | Cleared | 11/29/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 12/6/2022 | STEVE MELGAR |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/5/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 6/5/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 6/27/2023 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 6/27/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 6/28/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/24/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 8/24/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 8/24/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 8/24/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/25/2023 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 8/25/2023 | Approved | SABAS ALONSO |
| Insulation | 8/28/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 9/8/2023 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 9/8/2023 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 10/19/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Final | 11/6/2023 | Approved | SABAS ALONSO |
| Final | 11/6/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 11/6/2023 | Approved | SABAS ALONSO |
| HVAC-Final | 11/6/2023 | Approved | SABAS ALONSO |
| PLUMBING-Final | 11/6/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/6/2023 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 11/6/2023 | Approved | SABAS ALONSO |
| Smoke Detectors | 11/6/2023 | Approved | SABAS ALONSO |
| Final | 11/13/2023 | OK to Issue CofO | SABAS ALONSO |