19158 W CANTARA ST 91335
Certificate Information: 19158 W CANTARA ST 91335
- Application / Permit
- 22010-20000-05094
- Plan Check / Job No.
- B22VN15510
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan PROPOSED 1 STORY SFD PER SB 9 AND WFPP
- Permit Issued
- Issued on 10/25/2023
- Issuing Office
- Current Status
- CofO Issued on 11/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 11/17/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 11/22/2022 | GARO TELMI |
| Applicant returned to address corrections | 10/17/2023 | CRYSTEL MAALOUF |
| Plan Check Approved | 10/24/2023 | CRYSTEL MAALOUF |
| Issued | 10/25/2023 | APPLICANT |
| CofO in Progress | 9/11/2024 | DAVID SCANTLIN |
| Permit Finaled | 11/21/2024 | JOHN JANSON |
| CofO Issued | 11/21/2024 | JOHN JANSON |
| Permit Finaled | 11/21/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/13/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/14/2023 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 6/27/2023 | MATTHEW CRAIG |
| Senate Bill 9 | Cleared | 9/21/2023 | NATHAN ROMINE |
| Low Impact Development | Cleared | 10/2/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/4/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/27/2023 | Approved | JEFFREY BULL |
| Underground Mechanical | 11/27/2023 | Partial Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 12/15/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 12/15/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 12/15/2023 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 12/28/2023 | Corrections Issued | MORRIS JACKSON |
| Shower Pan | 12/28/2023 | Approved | MORRIS JACKSON |
| Wood Frame | 12/28/2023 | Not Ready for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 1/2/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 1/2/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 1/2/2024 | Approved | JEFFREY BULL |
| Verify Sprinkler Sign Off | 1/2/2024 | Approved | JEFFREY BULL |
| Insulation | 1/5/2024 | Approved | JEFFREY BULL |
| Drywall Nailing | 1/9/2024 | Approved | JEFFREY BULL |
| Sewer | 2/16/2024 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 2/16/2024 | Approved | ALEXANDER HANDY |
| Final | 7/3/2024 | No Access for Inspection | MORRIS JACKSON |
| Green Building Final | 7/3/2024 | No Access for Inspection | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 7/3/2024 | SGSOV Not Ready | MORRIS JACKSON |
| Service/Power Release | 7/3/2024 | No Access for Inspection | MORRIS JACKSON |
| Smoke Detectors | 7/3/2024 | No Access for Inspection | MORRIS JACKSON |
| Final | 7/10/2024 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 7/10/2024 | Not Ready for Inspection | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 7/10/2024 | Approved | JEFFREY BULL |
| Smoke Detectors | 7/10/2024 | Approved | JEFFREY BULL |
| Final | 9/11/2024 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 9/11/2024 | Approved | DAVID SCANTLIN |