459-459 1/2 E 30TH ST 90011
Certificate Information: 459-459 1/2 E 30TH ST 90011
- Application / Permit
- 22010-20000-05081
- Plan Check / Job No.
- B22VN14984
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 40' X 44'-4" 2-STORY DUPLEX WITH ATTACHED GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/11/2023
- Issuing Office
- Current Status
- CofO Issued on 11/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | RAPHAEL ROSAS |
| Corrections Issued | 10/15/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 10/21/2022 | STEVEN KIM |
| Applicant returned to address corrections | 1/19/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 1/30/2023 | RAPHAEL ROSAS |
| Issued | 4/11/2023 | APPLICANT |
| CofO in Progress | 11/28/2023 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 11/30/2023 | DEROLD HAUFF |
| Permit Finaled | 11/30/2023 | DEROLD HAUFF |
| CofO Issued | 11/30/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/29/2022 | RUEL COLE |
| Address approval | Cleared | 10/31/2022 | CELINA MORENO |
| Sewer availability | Cleared | 10/31/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2022 | CELINA MORENO |
| Low Impact Development | Cleared | 11/29/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 12/1/2022 | TREVOR QUAN |
| SB8 RUD | Cleared | 12/5/2022 | JAMES MCCARTHY |
| Highway dedication | Cleared | 1/9/2023 | TREVOR QUAN |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/2/2023 | Approved | BRENDAN MORELLI |
| Deputy Reinf. Concrete | 5/5/2023 | Conditional Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 6/1/2023 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 6/1/2023 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2023 | Partial Approval | BRENDAN MORELLI |
| Insulation | 6/2/2023 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 7/26/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/26/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/27/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/27/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 7/27/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 7/27/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/1/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/1/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/4/2023 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 8/4/2023 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/11/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 8/11/2023 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 9/5/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 10/13/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/22/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/22/2023 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 11/22/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 11/22/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 11/22/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/22/2023 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 11/22/2023 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/22/2023 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 11/22/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/25/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/25/2023 | Approved | ALEJANDRO DE ARTOLA |