11336 W TIARA ST 91601
Certificate Information: 11336 W TIARA ST 91601
- Application / Permit
- 22010-20000-05079
- Plan Check / Job No.
- B22VN14965
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SINGLE FAMILY RESIDENCE WITH ATTACHED 3- CAR GARAGE
- Permit Issued
- Issued on 7/17/2024
- Issuing Office
- Current Status
- Issued on 7/17/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | CARLOS MONTES |
| Corrections Issued | 10/16/2022 | CARLOS MONTES |
| Quality Review Completed | 10/19/2022 | GARO TELMI |
| Applicant returned to address corrections | 4/26/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 12/6/2023 | CARLOS MONTES |
| Plan Check Approved | 2/8/2024 | CARLOS MONTES |
| Issued | 7/17/2024 | APPLICANT |
Permit Application Clearance Information
| Highway dedication | Cleared | 10/20/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2023 | MEGAN GODINEZ |
| Address approval | Cleared | 8/29/2023 | DAGOVERTO GUERRERO |
| Frnt yard landscape/Water mgmt | Cleared | 8/31/2023 | SPENCER WEJROWSKI |
| Sewer availability | Cleared | 9/5/2023 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 11/9/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 11/13/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 11/14/2023 | JUSTIN BICOL |
Contact Information
| Contractor | A-1 Steel Erector; Lic. No.: 931279-B | 9414 ZAMORA AVENUE LOS ANGELES, CA 90002 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/5/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 9/11/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 10/1/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 10/16/2024 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 10/16/2024 | Partial Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 10/21/2024 | No Access for Inspection | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 10/24/2024 | Approved | JOSE AVILA |
| Deputy Drilled-In Anchors | 10/31/2024 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 11/4/2024 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 11/7/2024 | Not Ready for Inspection | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 11/8/2024 | Approved | JOSE AVILA |
| Deputy Drilled-In Anchors | 12/9/2024 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2024 | Partial Approval | JOSE AVILA |
| Deputy Drilled-In Anchors | 12/20/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2024 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2025 | Corrections Issued | JOSE AVILA |
| Deputy Wood Construction | 4/7/2025 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 4/8/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 5/30/2025 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/6/2025 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Rough | 6/6/2025 | Not Ready for Inspection | JOSE AVILA |
| Service/Power Release | 6/6/2025 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Rough | 6/13/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 6/13/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 6/18/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 6/18/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 6/24/2025 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Rough | 6/24/2025 | Not Ready for Inspection | JOSE AVILA |
| ELECTRICAL-Rough | 7/7/2025 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 7/7/2025 | Not Ready for Inspection | JOSE AVILA |
| Green Building Rough | 7/21/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 7/21/2025 | Partial Approval | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 7/21/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/22/2025 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/20/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 9/2/2025 | Partial Approval | JOSE AVILA |
| Drywall Nailing | 9/8/2025 | Partial Inspection | JOSE AVILA |
| Shower Pan | 11/4/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 11/18/2025 | Approved | JOSE AVILA |
| Underground Mechanical | 11/18/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 1/28/2026 | Approved | JOSE AVILA |
| Special/Order Compliance | 3/16/2026 | Corrections Issued | GAREN HAYRAPETYAN |