11336 W TIARA ST 91601

Certificate Information: 11336 W TIARA ST 91601

Application / Permit
22010-20000-05079
Plan Check / Job No.
B22VN14965
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SINGLE FAMILY RESIDENCE WITH ATTACHED 3- CAR GARAGE
Permit Issued
Issued on 7/17/2024
Issuing Office
Current Status
Issued on 7/17/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/12/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 CARLOS MONTES
Corrections Issued 10/16/2022 CARLOS MONTES
Quality Review Completed 10/19/2022 GARO TELMI
Applicant returned to address corrections 4/26/2023 CARLOS MONTES
Applicant returned to address corrections 12/6/2023 CARLOS MONTES
Plan Check Approved 2/8/2024 CARLOS MONTES
Issued 7/17/2024 APPLICANT

Permit Application Clearance Information

Highway dedication Cleared 10/20/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 1/30/2023 MEGAN GODINEZ
Address approval Cleared 8/29/2023 DAGOVERTO GUERRERO
Frnt yard landscape/Water mgmt Cleared 8/31/2023 SPENCER WEJROWSKI
Sewer availability Cleared 9/5/2023 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 11/9/2023 KURT CORRAL
Low Impact Development Cleared 11/13/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 11/14/2023 JUSTIN BICOL

Contact Information

Contractor A-1 Steel Erector; Lic. No.: 931279-B 9414 ZAMORA AVENUE      LOS ANGELES, CA 90002
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/5/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 9/11/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 10/1/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 10/16/2024 Corrections Issued JOSE AVILA
Underground Mechanical 10/16/2024 Partial Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 10/21/2024 No Access for Inspection JOSE AVILA
Excavation/Setback/Form/Re-Bar 10/24/2024 Approved JOSE AVILA
Deputy Drilled-In Anchors 10/31/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 11/4/2024 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 11/7/2024 Not Ready for Inspection JOSE AVILA
Excavation/Setback/Form/Re-Bar 11/8/2024 Approved JOSE AVILA
Deputy Drilled-In Anchors 12/9/2024 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Partial Approval JOSE AVILA
Deputy Drilled-In Anchors 12/20/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/24/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/28/2025 Corrections Issued JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/12/2025 Corrections Issued JOSE AVILA
Deputy Wood Construction 4/7/2025 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 4/8/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 5/30/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 6/6/2025 Not Ready for Inspection JOSE AVILA
HVAC-Rough 6/6/2025 Not Ready for Inspection JOSE AVILA
Service/Power Release 6/6/2025 Not Ready for Inspection JOSE AVILA
HVAC-Rough 6/13/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 6/13/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 6/18/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 6/18/2025 Approved JOSE AVILA
ELECTRICAL-Rough 6/24/2025 Not Ready for Inspection JOSE AVILA
HVAC-Rough 6/24/2025 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 7/7/2025 Corrections Issued JOSE AVILA
HVAC-Rough 7/7/2025 Not Ready for Inspection JOSE AVILA
Green Building Rough 7/21/2025 Approved JAVIER RAMOS JR
HVAC-Rough 7/21/2025 Partial Approval JAVIER RAMOS JR
Verify Sprinkler Sign Off 7/21/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 7/22/2025 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 8/20/2025 Approved JOSE AVILA
Drywall Nailing 9/2/2025 Partial Approval JOSE AVILA
Drywall Nailing 9/8/2025 Partial Inspection JOSE AVILA
Shower Pan 11/4/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 11/18/2025 Approved JOSE AVILA
Underground Mechanical 11/18/2025 Approved JOSE AVILA
Drywall Nailing 1/28/2026 Approved JOSE AVILA
Special/Order Compliance 3/16/2026 Corrections Issued GAREN HAYRAPETYAN