427 N BUNDY DR 90049

Certificate Information: 427 N BUNDY DR 90049

Application / Permit
22010-20000-05037
Plan Check / Job No.
B22VN15292
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ BASEMENT & ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 12/6/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 NILOOFAR MEHRAIN
Corrections Issued 10/25/2022 NILOOFAR MEHRAIN
Quality Review Completed 10/27/2022 STEVEN KIM
Building Plans Picked Up 10/28/2022 APPLICANT
Applicant returned to address corrections 12/13/2022 NILOOFAR MEHRAIN
Plan Check Approved 5/19/2023 NILOOFAR MEHRAIN
Issued 12/6/2023 APPLICANT
CofO in Progress 5/11/2025 CARLOS MATAMOROS
Permit Finaled 5/15/2025 RICHARD STEINBACH
CofO Issued 5/15/2025 RICHARD STEINBACH
Permit Finaled 5/15/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 11/2/2022 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 11/2/2022 HISASHI KOBAYAKAWA
Permit Cleared 11/2/2022 HISASHI KOBAYAKAWA
Sewer availability Cleared 11/2/2022 HISASHI KOBAYAKAWA
Trees in Parkway Cleared 11/8/2022 ADALBERTO VERA
Excavation more than 5-ft deep Cleared 11/15/2022 CALOSHA APPROVED
Hydrant and Access approval Cleared 11/19/2022 JOHN CONNEALLY
GPI Written Notices Cleared 12/13/2022 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 12/13/2022 NILOOFAR MEHRAIN
Low Impact Development Cleared 2/28/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 3/1/2023 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/15/2024 Partial Approval CARLOS MATAMOROS
Grounding or Bonding 2/15/2024 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 2/16/2024 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 3/6/2024 Partial Approval CARLOS MATAMOROS
Deputy Shotcrete 3/13/2024 Conditional Approval CARLOS MATAMOROS
PLUMBING-Rough 3/15/2024 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 4/1/2024 Partial Approval CHRISTOPHER WILSON
Deputy Wood Construction 4/18/2024 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 4/30/2024 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 5/7/2024 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 7/8/2024 Approved CARLOS MATAMOROS
Gas Test 7/12/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 7/12/2024 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 7/22/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 7/26/2024 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 7/26/2024 Approved CARLOS MATAMOROS
HVAC-Rough 7/29/2024 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 7/30/2024 Approved CARLOS MATAMOROS
Green Building Rough 7/30/2024 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 8/2/2024 Partial Approval CARLOS MATAMOROS
Insulation 8/9/2024 Approved CARLOS MATAMOROS
Drywall Nailing 8/22/2024 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 8/22/2024 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 9/5/2024 Approved CARLOS MATAMOROS
Sewer 10/28/2024 Approved CARLOS MATAMOROS
Underground Mechanical 10/28/2024 Approved CARLOS MATAMOROS
PLUMBING-Final 4/14/2025 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 4/15/2025 Corrections Issued STEPHANIE SWANSON
HVAC-Final 4/17/2025 Partial Approval MEL KHACHATOURIAN
Final 4/24/2025 Corrections Issued CARLOS MATAMOROS
Green Building Final 4/24/2025 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 4/24/2025 SGSOV Not Ready CARLOS MATAMOROS
Service/Power Release 4/24/2025 Not Ready for Inspection CARLOS MATAMOROS
Smoke Detectors 4/24/2025 Approved CARLOS MATAMOROS
Service/Power Release 5/2/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Final 5/9/2025 Approved CARLOS MATAMOROS
Final 5/9/2025 OK to Issue CofO CARLOS MATAMOROS
Gas Test 5/9/2025 Approved CARLOS MATAMOROS
HVAC-Final 5/9/2025 Approved CARLOS MATAMOROS
PLUMBING-Final 5/9/2025 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 5/9/2025 SGSOV Approved CARLOS MATAMOROS