5105 N GAVIOTA AVE 91436
Certificate Information: 5105 N GAVIOTA AVE 91436
- Application / Permit
- 22010-20000-05026
- Plan Check / Job No.
- B22VN15275
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 18' X 32' DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/3/2023
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 7/26/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | RAPHAEL ROSAS |
| Corrections Issued | 11/1/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 11/4/2022 | STEVEN KIM |
| Building Plans Picked Up | 11/7/2022 | APPLICANT |
| Applicant returned to address corrections | 2/13/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/7/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 3/9/2023 | RAPHAEL ROSAS |
| Issued | 5/3/2023 | APPLICANT |
| CofO in Progress | 7/26/2024 | THOMAS FINNILA |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 1/10/2023 | KURT CORRAL |
| Address approval | Cleared | 1/13/2023 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 1/13/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 1/13/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/18/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/5/2023 | Partial Approval | VINCENT HANLEY |
| Sewer | 6/5/2023 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/8/2023 | Partial Approval | VINCENT HANLEY |
| Sewer | 6/8/2023 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/20/2023 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2023 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 8/29/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 9/14/2023 | Approved | VINCENT HANLEY |
| HVAC-Rough | 9/29/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/4/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 10/4/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/23/2023 | Approved | SEAN HAUPT |
| Shower Pan | 10/23/2023 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 10/31/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/31/2023 | Approved | VINCENT HANLEY |
| Insulation | 10/31/2023 | Approved | VINCENT HANLEY |
| Drywall Nailing | 11/16/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/16/2023 | Approved | VINCENT HANLEY |
| Green Building Final | 6/21/2024 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 6/21/2024 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 6/21/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 7/2/2024 | OK to Issue CofO | THOMAS FINNILA |
| Green Building Final | 7/2/2024 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/2/2024 | SGSOV Approved | THOMAS FINNILA |
| Service/Power Release | 7/2/2024 | Approved | THOMAS FINNILA |
| Smoke Detectors | 7/2/2024 | Approved | THOMAS FINNILA |