4730 N COLUMBUS AVE 91403
Certificate Information: 4730 N COLUMBUS AVE 91403
- Application / Permit
- 22010-20000-04997
- Plan Check / Job No.
- B22VN15191
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 10' 10" X 13' PATIO COVER ATTACHED TO 5' 6" X 13' FULL BATHROOM (EXTERIOR ACCESS ONLY). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 12/23/2022
- Issuing Office
- Current Status
- CofO Issued on 9/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2022 | SERGIO MUNIZ |
| Corrections Issued | 10/15/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 10/21/2022 | APPLICANT |
| Applicant returned to address corrections | 11/17/2022 | ANGELICA DAVE |
| Applicant returned to address corrections | 11/18/2022 | JESSE ARELLANO |
| Plan Check Approved | 12/16/2022 | GURUNATH NESARAJAH |
| Issued | 12/23/2022 | APPLICANT |
| CofO in Progress | 8/10/2023 | THOMAS FINNILA |
| CofO Issued | 9/18/2023 | RUBEN SALAS |
| Permit Finaled | 9/18/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 10/25/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 10/25/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 10/25/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 10/25/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 10/25/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 10/31/2022 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 11/17/2022 | LUIS LUVANO |
Contact Information
| Contractor | Nork Construction Inc; Lic. No.: 1058592-B | 17204 CHATSWORTH ST #10 GRANADA HILLS, CA 91344 |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/2/2023 | Approved | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 2/6/2023 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/15/2023 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 2/15/2023 | Approved | THOMAS FINNILA |
| Insulation | 2/17/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 2/17/2023 | Partial Approval | THOMAS FINNILA |
| Drywall Nailing | 2/22/2023 | Approved | THOMAS FINNILA |
| Shower Pan | 2/27/2023 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/30/2023 | Approved | JOHN COLEMAN |
| Shower Pan | 3/30/2023 | Approved | JOHN COLEMAN |
| ELECTRICAL-Final | 6/27/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 6/27/2023 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/25/2023 | Approved | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/25/2023 | Approved | THOMAS FINNILA |
| Green Building Rough | 7/25/2023 | Approved | THOMAS FINNILA |
| HVAC-Final | 7/25/2023 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 7/25/2023 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 7/25/2023 | Approved | THOMAS FINNILA |
| Final | 7/31/2023 | OK to Issue CofO | THOMAS FINNILA |
| Green Building Final | 7/31/2023 | Approved | THOMAS FINNILA |
| HVAC-Final | 7/31/2023 | Approved | THOMAS FINNILA |
| MERV13>=Final | 7/31/2023 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/31/2023 | SGSOV Approved | THOMAS FINNILA |
| Service/Power Release | 7/31/2023 | Approved | THOMAS FINNILA |
| Smoke Detectors | 7/31/2023 | Approved | THOMAS FINNILA |