18214 W ACRE ST 91325

Certificate Information: 18214 W ACRE ST 91325

Application / Permit
22010-20000-04955
Plan Check / Job No.
B22VN15047
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 44' X 43'9" DETACHED ACCESSORY DWELLING UNIT TYPE V-A WITH ATTACHED TWO CAR GARAGE AS PER LAMC.12.22.33 (C) AND (E), NFPA-13D FIRE SPRINKLERS , ALL WORK PER WFPP- SEE COMMENTS
Permit Issued
Issued on 8/4/2023
Issuing Office
Current Status
CofO Issued on 11/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 RARES BODEA
Corrections Issued 11/3/2022 RARES BODEA
Quality Review Completed 11/4/2022 STEVEN KIM
Building Plans Picked Up 12/15/2022 APPLICANT
Applicant returned to address corrections 2/7/2023 RARES BODEA
Applicant returned to address corrections 2/23/2023 RARES BODEA
Applicant returned to address corrections 3/7/2023 RARES BODEA
Applicant returned to address corrections 5/16/2023 RARES BODEA
Applicant returned to address corrections 8/1/2023 RARES BODEA
Plan Check Approved 8/4/2023 RARES BODEA
Issued 8/4/2023 APPLICANT
CofO in Progress 10/23/2024 DAVID SCANTLIN
CofO in Progress 10/30/2024 JOHN JANSON
Permit Finaled 11/4/2024 JOHN JANSON
CofO Issued 11/4/2024 JOHN JANSON
Permit Finaled 11/4/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/21/2022 LEE GUILBEAUX
Miscellaneous Cleared 11/21/2022 LEE GUILBEAUX
Tract Map conditions Cleared 11/21/2022 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 11/22/2022 LEE GUILBEAUX
Sewer availability Cleared 11/22/2022 LEE GUILBEAUX
Hydrant and Access approval Cleared 12/13/2022 MATTHEW CRAIG
Low Impact Development Cleared 1/18/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 1/18/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/18/2023 LEE GUILBEAUX
Construction within easement Cleared 3/31/2023 WALTER RAMIREZ
Highway dedication Cleared 8/3/2023 LEE GUILBEAUX
Miscellaneous Cleared 8/3/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/21/2023 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 9/27/2023 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Not Ready for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 1/23/2024 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 1/25/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 1/31/2024 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 1/31/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 1/31/2024 Approved DAVID SCANTLIN
Drywall Nailing 2/12/2024 Approved KRISTEN CAUSEY
Green Building Rough 2/12/2024 Approved KRISTEN CAUSEY
Shower Pan 2/12/2024 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 2/22/2024 Approved DAVID SCANTLIN
Underground Mechanical 3/28/2024 Approved KRISTEN CAUSEY
ELECTRICAL-Final 8/15/2024 Partial Inspection KRISTEN CAUSEY
Service/Power Release 8/15/2024 Partial Inspection KRISTEN CAUSEY
Final 8/30/2024 Not Ready for Inspection KRISTEN CAUSEY
Verify Sprinkler Sign Off 8/30/2024 Approved KRISTEN CAUSEY
ELECTRICAL-Final 9/26/2024 Approved DAVID SCANTLIN
HVAC-Final 9/26/2024 Approved DAVID SCANTLIN
PLUMBING-Final 9/26/2024 Approved DAVID SCANTLIN
Service/Power Release 9/26/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 10/2/2024 Approved DAVID SCANTLIN
Final 10/2/2024 Corrections Issued DAVID SCANTLIN
Green Building Final 10/2/2024 Not Ready for Inspection DAVID SCANTLIN
HVAC-Final 10/2/2024 Approved DAVID SCANTLIN
PLUMBING-Final 10/2/2024 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 10/2/2024 SGSOV No Gas DAVID SCANTLIN
Service/Power Release 10/2/2024 Approved DAVID SCANTLIN
Smoke Detectors 10/2/2024 Approved DAVID SCANTLIN
Final 10/23/2024 OK to Issue CofO DAVID SCANTLIN
Green Building Final 10/23/2024 Approved DAVID SCANTLIN