19237-19239 W BERCLAIR LANE 91356
Certificate Information: 19237-19239 W BERCLAIR LANE 91356
- Application / Permit
- 22010-20000-04951
- Plan Check / Job No.
- B22VN15042
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY (90'-6"x100'-6"), 5160 SQFT SINGLE FAMILY DWELLING WITH ATTACHED 3 CAR GARAGE (592 SQFT) AND ATTACHED ADU (1000 SQFT) AND ADD ATTACHED OPEN TRELLIS. PER LAMC 12.22 A.33(c)(e) W/NPFA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 6/2/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | PETER MOSESIAN |
| Corrections Issued | 10/16/2022 | PETER MOSESIAN |
| Quality Review Completed | 10/18/2022 | OMID HEDAYAT |
| Plan Check Approved | 4/5/2023 | PETER MOSESIAN |
| No Progress | 5/30/2023 | PETER MOSESIAN |
| Issued | 6/2/2023 | APPLICANT |
| CofO in Progress | 1/7/2025 | JOHN KIDWELL |
| Permit Finaled | 1/9/2025 | JOHN JANSON |
| CofO Issued | 1/9/2025 | JOHN JANSON |
| Permit Finaled | 1/9/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/21/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/21/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/21/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/21/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/21/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/21/2022 | CARLOS AGUILERA |
| Street Frontage | Cleared | 12/21/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/27/2022 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 1/5/2023 | ADALBERTO VERA |
| Permit | Cleared | 1/25/2023 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 2/10/2023 | GILBERT URREA |
| Low Impact Development | Cleared | 3/17/2023 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 3/20/2023 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 4/5/2023 | PETER MOSESIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cai,, Luo; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Engineer | Elia,, Victor Anthony; Lic. No.: C64803 | 40912 CARLENA LN TEMECULA, CA 92591 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/6/2023 | Partial Inspection | MORRIS JACKSON |
| Underground Mechanical | 9/6/2023 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 9/13/2023 | Not Ready for Inspection | SEAN HAUPT |
| Footing/Foundation/Slab | 9/13/2023 | Not Ready for Inspection | SEAN HAUPT |
| Deputy Reinf. Concrete | 9/15/2023 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 9/15/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 9/15/2023 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 9/19/2023 | Approved | SEAN HAUPT |
| Deputy Reinf. Concrete | 9/26/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 9/26/2023 | Approved | SEAN HAUPT |
| Structural Steel Frame | 9/26/2023 | Partial Approval | SEAN HAUPT |
| Deputy Drilled-In Anchors | 10/16/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2023 | Approved | SEAN HAUPT |
| Structural Steel Frame | 10/16/2023 | Approved | SEAN HAUPT |
| Wood Frame | 10/16/2023 | Approved | SEAN HAUPT |
| Deputy Steel/Welding | 10/30/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2023 | Approved | SEAN HAUPT |
| HVAC-Rough | 11/17/2023 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 11/17/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Approved | SEAN HAUPT |
| Gas Test | 12/18/2023 | Partial Approval | SEAN HAUPT |
| HVAC-Rough | 12/18/2023 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 12/18/2023 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 12/22/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2023 | Not Ready for Inspection | SEAN HAUPT |
| Shower Pan | 12/29/2023 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 1/18/2024 | Not Ready for Inspection | SEAN HAUPT |
| Deputy Wood Construction | 1/18/2024 | Approved | SEAN HAUPT |
| Green Building Rough | 1/18/2024 | Not Ready for Inspection | SEAN HAUPT |
| Interior/Exterior Lathing | 1/18/2024 | Not Ready for Inspection | SEAN HAUPT |
| Verify Sprinkler Sign Off | 1/18/2024 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 2/2/2024 | Approved | SEAN HAUPT |
| Green Building Rough | 2/2/2024 | Approved | SEAN HAUPT |
| Insulation | 2/2/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 2/2/2024 | Approved | SEAN HAUPT |
| Structural Steel Frame | 2/2/2024 | Approved | SEAN HAUPT |
| Verify Rec and Parks Fee Memo | 2/2/2024 | Approved | SEAN HAUPT |
| Wood Frame | 2/2/2024 | Approved | SEAN HAUPT |
| Drywall Nailing | 2/9/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 2/9/2024 | Approved | SEAN HAUPT |
| Gas Test | 5/14/2024 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 8/6/2024 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Final | 8/6/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Service/Power Release | 8/6/2024 | Corrections Issued | JOHN KIDWELL |
| ELECTRICAL-Final | 8/20/2024 | Approved | JOHN KIDWELL |
| HVAC-Final | 8/20/2024 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Final | 8/20/2024 | Approved | JOHN KIDWELL |
| Service/Power Release | 8/22/2024 | Approved | JOHN KIDWELL |
| Special/Order Compliance | 9/9/2024 | Partial Inspection | JOHN KIDWELL |
| HVAC-Final | 10/9/2024 | Approved | JOHN KIDWELL |
| Final | 12/23/2024 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 12/23/2024 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 12/23/2024 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 12/23/2024 | Approved | JOHN KIDWELL |