1013 W 70TH ST 90044
Certificate Information: 1013 W 70TH ST 90044
- Application / Permit
- 22010-20000-04941
- Plan Check / Job No.
- B22VN15004
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30' X 20'-2" TWO STORY ACCESSORY DWELLING UNIT WITH ATTACHED CARPORT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 12/27/2022
- Issuing Office
- Current Status
- CofO Issued on 12/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | SELLA BENYAMIN |
| Corrections Issued | 10/17/2022 | SELLA BENYAMIN |
| Quality Review Completed | 10/19/2022 | STEVEN KIM |
| Building Plans Picked Up | 10/20/2022 | APPLICANT |
| Plan Check Approved | 12/27/2022 | SELLA BENYAMIN |
| Issued | 12/27/2022 | APPLICANT |
| CofO in Progress | 11/26/2024 | CRAIG DAVIS |
| Permit Finaled | 12/7/2024 | DEROLD HAUFF |
| CofO Issued | 12/7/2024 | DEROLD HAUFF |
| Permit Finaled | 12/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/22/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 11/14/2022 | JEANETTE VONG |
| Community Plan Implem. Overlay | Cleared | 12/5/2022 | RAFAEL FONTES |
| ZI | Cleared | 12/5/2022 | RAFAEL FONTES |
| Low Impact Development | Cleared | 12/12/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 12/15/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/21/2023 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/30/2023 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 8/31/2023 | Approved | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 9/1/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Partial Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 2/20/2024 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2024 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Rough | 2/20/2024 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 2/23/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 2/23/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 2/23/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Wood Frame | 2/23/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 2/26/2024 | Conditional Approval | RONNIE MINDANAO |
| PLUMBING-Rough | 2/28/2024 | Corrections Issued | RONNIE MINDANAO |
| Wood Frame | 2/28/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 3/13/2024 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/13/2024 | Conditional Approval | JOSEPH MCGARRY |
| Green Building Rough | 3/13/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 3/13/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/13/2024 | Approved | JOSEPH MCGARRY |
| Deputy Wood Construction | 3/14/2024 | Conditional Approval | CRAIG DAVIS |
| Interior/Exterior Lathing | 3/19/2024 | Partial Approval | CRAIG DAVIS |
| Shower Pan | 3/19/2024 | Corrections Issued | CRAIG DAVIS |
| Insulation | 3/26/2024 | Corrections Issued | CRAIG DAVIS |
| Insulation | 3/29/2024 | Corrections Issued | CRAIG DAVIS |
| Insulation | 4/10/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 4/10/2024 | Approved | JOSH MEISTER |
| Shower Pan | 4/10/2024 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 4/12/2024 | Corrections Issued | CRAIG DAVIS |
| Drywall Nailing | 4/12/2024 | Partial Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 4/12/2024 | Corrections Issued | CRAIG DAVIS |
| Interior/Exterior Lathing | 4/12/2024 | Approved | CRAIG DAVIS |
| Underground Mechanical | 6/13/2024 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 6/25/2024 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 7/25/2024 | Not Ready for Inspection | JOSE MACIAS |
| Final | 7/25/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 7/25/2024 | Not Ready for Inspection | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 7/25/2024 | SGSOV Not Ready | JOSE MACIAS |
| Service/Power Release | 7/25/2024 | Not Ready for Inspection | JOSE MACIAS |
| Smoke Detectors | 7/25/2024 | Not Ready for Inspection | JOSE MACIAS |
| BUILDING-Rough-Frame | 8/16/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 8/16/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 8/16/2024 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 8/16/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Service/Power Release | 8/16/2024 | Corrections Issued | CRAIG DAVIS |
| Smoke Detectors | 8/16/2024 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 8/23/2024 | Partial Inspection | MICHAEL LEWIS |
| Final | 8/23/2024 | Partial Inspection | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 8/23/2024 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 8/23/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/17/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 9/17/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Service/Power Release | 9/17/2024 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 10/25/2024 | Approved | CRAIG DAVIS |
| Final | 10/25/2024 | Corrections Issued | CRAIG DAVIS |
| Service/Power Release | 10/25/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 11/13/2024 | Corrections Issued | CRAIG DAVIS |
| Service/Power Release | 11/13/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Final | 11/25/2024 | Approved | CRAIG DAVIS |
| Final | 11/25/2024 | OK to Issue CofO | CRAIG DAVIS |
| Gas Test | 11/25/2024 | Approved | CRAIG DAVIS |
| HVAC-Final | 11/25/2024 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 11/25/2024 | Approved | CRAIG DAVIS |
| Service/Power Release | 11/25/2024 | Approved | CRAIG DAVIS |