10432 N MILWOOD AVE 91311

Certificate Information: 10432 N MILWOOD AVE 91311

Application / Permit
22010-20000-04937
Plan Check / Job No.
B22VN14988
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN Adding a 2 story SFD to an existing 2-car attached garage *** Permit must be issued concurrently with SFD to ADU conversion permit ***
Permit Issued
Issued on 12/1/2023
Issuing Office
Current Status
Issued on 12/1/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/6/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 MARCELA FRANQUEZ
Corrections Issued 11/7/2022 MARCELA FRANQUEZ
Quality Review Completed 11/15/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 1/17/2023 MARCELA FRANQUEZ
Applicant returned to address corrections 4/4/2023 MARCELA FRANQUEZ
Plan Check Approved 9/12/2023 MARCELA FRANQUEZ
No Progress 11/8/2023 MARCELA FRANQUEZ
Plan Check Approved 11/8/2023 MARCELA FRANQUEZ
Issued 12/1/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/27/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 1/30/2023 COLIN LOREDO
Sewer availability Cleared 2/28/2023 ROSE MARIE SMITH
Grading Pre-Inspection Cleared 4/4/2023 MARCELA FRANQUEZ
Hydrant and Access approval Cleared 4/20/2023 RUEL COLE
Low Impact Development Cleared 8/18/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 8/22/2023 LEE GUILBEAUX
GPI Written Notices Cleared 9/12/2023 MARCELA FRANQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/11/2024 Not Ready for Inspection DAVID SCANTLIN
Footing/Foundation/Slab 1/18/2024 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 1/30/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 2/16/2024 Not Ready for Inspection KRISTEN CAUSEY
Green Building Rough 2/16/2024 Not Ready for Inspection KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 2/27/2024 Partial Approval DAVID SCANTLIN
Deputy Steel/Welding 3/11/2024 Conditional Approval DAVID SCANTLIN
Deputy Wood Construction 3/26/2024 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 3/29/2024 Approved DAVID SCANTLIN
Green Building Rough 3/29/2024 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 3/29/2024 Approved DAVID SCANTLIN
Insulation 4/4/2024 Partial Approval JEFFREY HARTLINE
Insulation 4/9/2024 Partial Approval DAVID SCANTLIN
Drywall Nailing 5/1/2024 Approved DAVID SCANTLIN
Final 11/1/2024 Corrections Issued DAVID SCANTLIN
Green Building Final 11/1/2024 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 11/1/2024 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 11/1/2024 Approved DAVID SCANTLIN
Deputy Drilled-In Anchors 5/28/2025 Approved DAVID SCANTLIN
Deputy Reinf. Concrete 5/29/2025 Conditional Approval DAVID SCANTLIN
Final 5/29/2025 Corrections Issued DAVID SCANTLIN