9310 N ORION AVE 91343

Certificate Information: 9310 N ORION AVE 91343

Application / Permit
22010-20000-04934
Plan Check / Job No.
B22VN14985
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN: NEW 34'8"X37'1" 1-STORY DETACHED ADU PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 3/14/2024
Issuing Office
Current Status
CofO Issued on 5/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 MARVEL DELACRUZ
Corrections Issued 10/19/2022 MARVEL DELACRUZ
Quality Review Completed 10/21/2022 OMID HEDAYAT
Applicant returned to address corrections 6/8/2023 MARVEL DELACRUZ
Applicant returned to address corrections 8/18/2023 MARVEL DELACRUZ
Plan Check Approved 9/28/2023 MARVEL DELACRUZ
Issued 3/14/2024 APPLICANT
CofO in Progress 4/28/2025 VINCENT HANLEY
Permit Finaled 5/13/2025 RUBEN SALAS
CofO Issued 5/13/2025 RUBEN SALAS
Permit Finaled 5/13/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/27/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/27/2022 LEE GUILBEAUX
Permit Cleared 10/27/2022 LEE GUILBEAUX
Sewer availability Cleared 4/5/2023 LEE GUILBEAUX
Trees in Parkway Cleared 7/31/2023 ADALBERTO VERA
Low Impact Development Cleared 8/22/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 8/25/2023 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 9/16/2023 JOHN CONNEALLY
Hydrant and Access approval Cleared 9/16/2023 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Niver,, Kenneth Earl; Lic. No.: S2554 10845 LINDBROOK DR STE 203      W LOS ANGELES, CA 90024

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/29/2024 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 6/3/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 6/3/2024 Approved VINCENT HANLEY
Sewer 7/30/2024 Approved VINCENT HANLEY
Underground Mechanical 7/30/2024 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/11/2024 Partial Approval VINCENT HANLEY
Underground Mechanical 9/11/2024 Partial Approval VINCENT HANLEY
ELECTRICAL-Final 10/3/2024 Approved VINCENT HANLEY
PLUMBING-Rough 10/3/2024 Approved VINCENT HANLEY
Shower Pan 10/3/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 10/10/2024 Approved VINCENT HANLEY
Green Building Rough 10/10/2024 Approved VINCENT HANLEY
HVAC-Rough 10/10/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 10/10/2024 Approved VINCENT HANLEY
MERV13>=Rough 10/10/2024 Approved VINCENT HANLEY
Insulation 10/24/2024 Approved VINCENT HANLEY
Drywall Nailing 10/31/2024 Approved VINCENT HANLEY
Final 4/2/2025 Corrections Issued VINCENT HANLEY
Green Building Final 4/2/2025 Approved VINCENT HANLEY
MERV13>=Final 4/2/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/2/2025 SGSOV Approved VINCENT HANLEY
Service/Power Release 4/2/2025 Approved VINCENT HANLEY
Smoke Detectors 4/2/2025 Approved VINCENT HANLEY
Final 4/28/2025 OK to Issue CofO VINCENT HANLEY
ELECTRICAL-Final 4/30/2025 Approved VINCENT HANLEY