9310 N ORION AVE 91343
Certificate Information: 9310 N ORION AVE 91343
- Application / Permit
- 22010-20000-04934
- Plan Check / Job No.
- B22VN14985
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN: NEW 34'8"X37'1" 1-STORY DETACHED ADU PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 3/14/2024
- Issuing Office
- Current Status
- CofO Issued on 5/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | MARVEL DELACRUZ |
| Corrections Issued | 10/19/2022 | MARVEL DELACRUZ |
| Quality Review Completed | 10/21/2022 | OMID HEDAYAT |
| Applicant returned to address corrections | 6/8/2023 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 8/18/2023 | MARVEL DELACRUZ |
| Plan Check Approved | 9/28/2023 | MARVEL DELACRUZ |
| Issued | 3/14/2024 | APPLICANT |
| CofO in Progress | 4/28/2025 | VINCENT HANLEY |
| Permit Finaled | 5/13/2025 | RUBEN SALAS |
| CofO Issued | 5/13/2025 | RUBEN SALAS |
| Permit Finaled | 5/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/27/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2022 | LEE GUILBEAUX |
| Permit | Cleared | 10/27/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/5/2023 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 7/31/2023 | ADALBERTO VERA |
| Low Impact Development | Cleared | 8/22/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 8/25/2023 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 9/16/2023 | JOHN CONNEALLY |
| Hydrant and Access approval | Cleared | 9/16/2023 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Niver,, Kenneth Earl; Lic. No.: S2554 | 10845 LINDBROOK DR STE 203 W LOS ANGELES, CA 90024 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/29/2024 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 6/3/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/3/2024 | Approved | VINCENT HANLEY |
| Sewer | 7/30/2024 | Approved | VINCENT HANLEY |
| Underground Mechanical | 7/30/2024 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2024 | Partial Approval | VINCENT HANLEY |
| Underground Mechanical | 9/11/2024 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Final | 10/3/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 10/3/2024 | Approved | VINCENT HANLEY |
| Shower Pan | 10/3/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/10/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/10/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 10/10/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/10/2024 | Approved | VINCENT HANLEY |
| MERV13>=Rough | 10/10/2024 | Approved | VINCENT HANLEY |
| Insulation | 10/24/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 10/31/2024 | Approved | VINCENT HANLEY |
| Final | 4/2/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 4/2/2025 | Approved | VINCENT HANLEY |
| MERV13>=Final | 4/2/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/2/2025 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 4/2/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 4/2/2025 | Approved | VINCENT HANLEY |
| Final | 4/28/2025 | OK to Issue CofO | VINCENT HANLEY |
| ELECTRICAL-Final | 4/30/2025 | Approved | VINCENT HANLEY |