2811 S WESTGATE AVE 90064

Certificate Information: 2811 S WESTGATE AVE 90064

Application / Permit
22010-20000-04925
Plan Check / Job No.
B22VN14976
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY 21'0"X35'0" IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 2/14/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 MARVEL DELACRUZ
Corrections Issued 11/4/2022 MARVEL DELACRUZ
Quality Review Completed 11/7/2022 OMID HEDAYAT
Building Plans Picked Up 11/8/2022 APPLICANT
Plan Check Approved 2/2/2023 MARVEL DELACRUZ
Issued 2/14/2023 APPLICANT
CofO in Progress 4/15/2024 JESUS PINEDA
Permit Finaled 4/16/2024 DANIEL ORRANTE
CofO Issued 4/16/2024 DANIEL ORRANTE
Permit Finaled 4/16/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/17/2022 JENSON LEE
Construction near power lines Cleared 12/1/2022 RIDWAN HARDY
Construction within easement Cleared 12/1/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 12/16/2022 KURT CORRAL
Low Impact Development Cleared 1/13/2023 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 1/19/2023 AHMED AMARRAGY
Roof/Waste drainage to street Cleared 1/24/2023 CATHERINE ADROVER
Sewer availability Cleared 1/24/2023 CATHERINE ADROVER
Green Code Cleared 2/2/2023 MARVEL DELACRUZ

Contact Information

Contractor Birdwell / Peck Construction Llc; Lic. No.: 911863-B 11524 BELLAGIO ROAD      LOS ANGELES, CA 90049
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/10/2023 Partial Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 7/14/2023 Approved JESUS PINEDA
Sewer 7/14/2023 Approved JESUS PINEDA
Excavation/Setback/Form/Re-Bar 7/20/2023 Approved JESUS PINEDA
ELECTRICAL-Rough 8/9/2023 Not Ready for Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Partial Approval JESUS PINEDA
Underground Mechanical 8/9/2023 Approved JESUS PINEDA
BUILDING-Rough-Frame 10/5/2023 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Rough 10/5/2023 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/5/2023 Approved JESUS PINEDA
Gas Test 10/5/2023 Approved JESUS PINEDA
Green Building Rough 10/5/2023 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 10/5/2023 Approved JESUS PINEDA
PLUMBING-Rough 10/5/2023 Approved JESUS PINEDA
Verify Sprinkler Sign Off 10/5/2023 Not Ready for Inspection JESUS PINEDA
BUILDING-Rough-Frame 10/26/2023 Approved JESUS PINEDA
ELECTRICAL-Rough 10/26/2023 Approved JESUS PINEDA
Green Building Rough 10/26/2023 Approved JESUS PINEDA
HVAC-Rough 10/26/2023 Approved JESUS PINEDA
Insulation 10/26/2023 Corrections Issued JESUS PINEDA
Interior/Exterior Lathing 10/26/2023 Partial Approval JESUS PINEDA
PLUMBING-Rough 10/26/2023 Approved JESUS PINEDA
Drywall Nailing 11/2/2023 Approved BEN MOLSTAD
Insulation 11/2/2023 Approved BEN MOLSTAD
Interior/Exterior Lathing 11/27/2023 Approved JESUS PINEDA
Shower Pan 11/27/2023 Approved JESUS PINEDA
ELECTRICAL-Final 1/16/2024 Corrections Issued JESUS PINEDA
Final 1/16/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 1/16/2024 Approved JESUS PINEDA
Gas Test 1/16/2024 Approved JESUS PINEDA
Green Building Final 1/16/2024 Approved JESUS PINEDA
HVAC-Final 1/16/2024 Corrections Issued JESUS PINEDA
PLUMBING-Final 1/16/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 1/16/2024 SGSOV Not Required JESUS PINEDA
Service/Power Release 1/16/2024 Not Ready for Inspection JESUS PINEDA
Smoke Detectors 1/16/2024 Approved JESUS PINEDA
ELECTRICAL-Final 4/15/2024 Approved JESUS PINEDA
Final 4/15/2024 OK to Issue CofO JESUS PINEDA
HVAC-Final 4/15/2024 Approved JESUS PINEDA
Service/Power Release 4/15/2024 Approved JESUS PINEDA