10940 N JAMIE AVE 91331
Certificate Information: 10940 N JAMIE AVE 91331
- Application / Permit
- 22010-20000-04902
- Plan Check / Job No.
- B22VN14913
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20'-0" X 24'-6" ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 6/20/2023
- Issuing Office
- Current Status
- CofO Issued on 9/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 10/8/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 10/14/2022 | APPLICANT |
| Applicant returned to address corrections | 5/1/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 6/20/2023 | RAMA DABADGE |
| Issued | 6/20/2023 | APPLICANT |
| CofO in Progress | 7/31/2024 | MICHEL ABAJAN |
| No Progress | 8/9/2024 | ROBERT GOLD |
| CofO in Progress | 8/9/2024 | ROBERT GOLD |
| CofO Issued | 9/5/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/5/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/3/2022 | LUCIA MERCADO |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2022 | LUCIA MERCADO |
| Sewer availability | Cleared | 11/3/2022 | LUCIA MERCADO |
| ZA Case | Cleared | 12/23/2022 | MAXFIELD VERMY |
| Hydrant and Access approval | Cleared | 2/4/2023 | GILBERT URREA |
| Low Impact Development | Cleared | 4/27/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 4/28/2023 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 5/1/2023 | ARTIN ZARUKIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/13/2023 | Corrections Issued | MICHEL ABAJAN |
| Pre-Inspection | 12/14/2023 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Rough | 1/9/2024 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 1/16/2024 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/16/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2024 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 2/27/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/22/2024 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/22/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 3/22/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/22/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 3/22/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/1/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 4/1/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/1/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Wood Frame | 4/1/2024 | Partial Inspection | MICHEL ABAJAN |
| Insulation | 4/2/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/2/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 4/5/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/21/2024 | Approved | MICHEL ABAJAN |
| Final | 5/21/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 5/21/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 5/21/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 5/21/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/21/2024 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 5/21/2024 | Not Required | MICHEL ABAJAN |
| Smoke Detectors | 5/21/2024 | Approved | MICHEL ABAJAN |
| Final | 7/1/2024 | Corrections Issued | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/1/2024 | SGSOV Approved | MICHEL ABAJAN |
| Final | 7/31/2024 | OK to Issue CofO | MICHEL ABAJAN |