9824 N WHEATLAND AVE 91040
Certificate Information: 9824 N WHEATLAND AVE 91040
- Application / Permit
- 22010-20000-04901
- Plan Check / Job No.
- B22VN14912
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 20' X 20' DETACHED 2-CAR GARAGE. WORK DONE PER ENGINEER.
- Permit Issued
- Issued on 9/15/2023
- Issuing Office
- Current Status
- CofO Issued on 2/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 10/9/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 3/10/2023 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 3/22/2023 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 9/13/2023 | PINANK PATEL |
| Plan Check Approved | 9/14/2023 | ROSENDO MEDINA |
| Issued | 9/15/2023 | APPLICANT |
| CofO in Progress | 2/5/2025 | DAVID ANDERSON |
| Permit Finaled | 2/18/2025 | RUBEN SALAS |
| CofO Issued | 2/18/2025 | RUBEN SALAS |
| Permit Finaled | 2/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 10/13/2022 | ASHLEY RODARTE |
| Miscellaneous | Cleared | 10/13/2022 | ASHLEY RODARTE |
| ZI | Cleared | 10/13/2022 | ASHLEY RODARTE |
| Grading Pre-Inspection | Cleared | 11/29/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2022 | CARLOS AGUILERA |
| Specific Plan | Cleared | 7/25/2023 | JOSHUA ORDONEZ |
| Roof/Waste drainage to street | Cleared | 8/3/2023 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 9/13/2023 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/1/2024 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 3/11/2024 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2024 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 4/17/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 5/3/2024 | Approved | DAVID ANDERSON |
| Insulation | 5/3/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 5/3/2024 | Approved | DAVID ANDERSON |
| Drywall Nailing | 5/14/2024 | Approved | DAVID ANDERSON |
| Final | 6/27/2024 | Corrections Issued | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 6/27/2024 | SGSOV Not Required | DAVID ANDERSON |
| Service/Power Release | 6/27/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 6/27/2024 | Approved | DAVID ANDERSON |
| Final | 2/4/2025 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 2/4/2025 | Approved | DAVID ANDERSON |