1260-1262 E 53RD ST 90011
Certificate Information: 1260-1262 E 53RD ST 90011
- Application / Permit
- 22010-20000-04891
- Plan Check / Job No.
- B22VN14879
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan: NEW 2-STORY DUPLEX & ATTACHED 3-CAR GARAGE
- Permit Issued
- Issued on 4/25/2023
- Issuing Office
- Current Status
- CofO Issued on 10/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | JAD BASMA |
| Corrections Issued | 10/10/2022 | JAD BASMA |
| Quality Review Completed | 10/19/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 1/3/2023 | JAD BASMA |
| No Progress | 3/13/2023 | JAD BASMA |
| Plan Check Approved | 4/7/2023 | JAD BASMA |
| Issued | 4/25/2023 | APPLICANT |
| CofO in Progress | 10/20/2023 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 10/29/2023 | DEROLD HAUFF |
| CofO Issued | 10/29/2023 | DEROLD HAUFF |
| Permit Finaled | 10/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/23/2022 | JEANETTE VONG |
| Permit | Cleared | 10/23/2022 | JEANETTE VONG |
| Trees in Parkway | Cleared | 10/28/2022 | ADALBERTO VERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 11/11/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 12/1/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 12/7/2022 | STEVE MELGAR |
| SB8 RUD | Cleared | 12/22/2022 | DORIS KWOK |
| Sewer availability | Cleared | 3/16/2023 | STEVE MELGAR |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | , ; Lic. No.: NA81695 | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 5/25/2023 | Partial Inspection | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 5/25/2023 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/2/2023 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 6/2/2023 | Partial Approval | BRENDAN MORELLI |
| Sewer | 6/2/2023 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Partial Approval | BRENDAN MORELLI |
| Insulation | 6/5/2023 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Partial Approval | BRENDAN MORELLI |
| Deputy Wood Construction | 6/23/2023 | Approved | DONALD CRICHLOW |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 6/29/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 6/29/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/7/2023 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 7/7/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 7/10/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 7/10/2023 | Approved | BRENDAN MORELLI |
| Green Building Rough | 7/10/2023 | Approved | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 7/10/2023 | Approved | BRENDAN MORELLI |
| Insulation | 7/17/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 7/17/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 7/26/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/26/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 9/7/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 9/11/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/26/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/17/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/17/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/17/2023 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 10/17/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/17/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/17/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/17/2023 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/17/2023 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/17/2023 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 10/17/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/18/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/18/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/18/2023 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/18/2023 | Approved | ALEJANDRO DE ARTOLA |