400 1/2 E 69TH ST 90003
Certificate Information: 400 1/2 E 69TH ST 90003
- Application / Permit
- 22010-20000-04882
- Plan Check / Job No.
- B22VN14843
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: NEW ONE STORY ADU. 1 of 2
- Permit Issued
- Issued on 7/29/2023
- Issuing Office
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | TSE MING HUANG |
| Corrections Issued | 10/20/2022 | TSE MING HUANG |
| Quality Review Completed | 10/24/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 7/7/2023 | TSE MING HUANG |
| Plan Check Approved | 7/28/2023 | TSE MING HUANG |
| Issued | 7/29/2023 | APPLICANT |
| CofO in Progress | 9/16/2024 | MICHAEL LEWIS |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/22/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2023 | WALLIE JONG |
| Construction near power lines | Cleared | 3/30/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/30/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/6/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 6/9/2023 | JEANIE LAM |
| Sewer availability | Cleared | 6/14/2023 | JEANIE LAM |
Contact Information
| Architect | , ; Lic. No.: C36231 | , |
| Contractor | Home Creations Inc; Lic. No.: 1057627-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/2/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 8/2/2023 | Approved | MICHAEL LEWIS |
| Sewer | 8/2/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 8/2/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 8/21/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 8/21/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 8/21/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 8/22/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 8/24/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 8/24/2023 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 8/24/2023 | Approved | MICHAEL LEWIS |
| Insulation | 8/28/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 8/28/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 9/1/2023 | Approved | STUART CHAPMAN |
| Final | 5/31/2024 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Not Ready | MICHAEL LEWIS |
| Service/Power Release | 5/31/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Smoke Detectors | 5/31/2024 | Approved | MICHAEL LEWIS |
| Final | 8/13/2024 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 8/13/2024 | SGSOV Not Ready | MICHAEL LEWIS |
| Service/Power Release | 8/13/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Final | 9/6/2024 | OK to Issue CofO | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 9/6/2024 | Approved | MICHAEL LEWIS |