5520 N SYLVIA AVE 91356
Certificate Information: 5520 N SYLVIA AVE 91356
- Application / Permit
- 22010-20000-04881
- Plan Check / Job No.
- B22VN14835
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 24'-0" x 35'-9" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 2/16/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2022 | JESSE ARELLANO |
| Corrections Issued | 10/6/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 10/18/2022 | APPLICANT |
| Plan Check Approved | 2/15/2023 | MIROOSH KHACHATOORIAN |
| Issued | 2/16/2023 | APPLICANT |
| CofO in Progress | 6/11/2024 | JOHN KIDWELL |
| Permit Finaled | 6/21/2024 | JOHN JANSON |
| CofO Issued | 6/21/2024 | JOHN JANSON |
| Permit Finaled | 6/21/2024 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/3/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/3/2022 | RIDWAN HARDY |
| Address approval | Cleared | 12/6/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 2/8/2023 | ERNEST TSE |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 2/9/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/9/2023 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 2/15/2023 | JESSE ARELLANO |
| Grading Pre-Inspection | Cleared | 2/15/2023 | JESSE ARELLANO |
Contact Information
| Contractor | Arbabi Construction Inc; Lic. No.: 514421-B | 21426 VELICATA STREET WOODLAND HILLS, CA 91364 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/23/2023 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 3/3/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| Special/Order Compliance | 3/3/2023 | Partial Inspection | MORRIS JACKSON |
| Footing/Foundation/Slab | 3/7/2023 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 4/7/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2023 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 4/7/2023 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 4/14/2023 | Partial Approval | DAVID SANDOVAL |
| HVAC-Rough | 4/14/2023 | Corrections Issued | DAVID SANDOVAL |
| HVAC-Rough | 4/21/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| Pre-Inspection | 4/21/2023 | Partial Inspection | JUSTIN HAWLEY |
| Insulation | 4/27/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 4/27/2023 | Approved | SEAN HAUPT |
| Shower Pan | 5/17/2023 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 8/1/2023 | Approved | SEAN HAUPT |
| Final | 8/1/2023 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 8/1/2023 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 8/1/2023 | Approved | SEAN HAUPT |
| MERV13>=Final | 8/1/2023 | Approved | SEAN HAUPT |
| MERV13>=Rough | 8/1/2023 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 8/1/2023 | SGSOV Not Ready | SEAN HAUPT |
| Service/Power Release | 8/1/2023 | Not Ready for Inspection | SEAN HAUPT |
| Smoke Detectors | 8/1/2023 | Not Ready for Inspection | SEAN HAUPT |
| Verify Sprinkler Sign Off | 8/1/2023 | Approved | SEAN HAUPT |
| Final | 1/9/2024 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Final | 1/9/2024 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 1/9/2024 | SGSOV Not Ready | SEAN HAUPT |
| Service/Power Release | 1/9/2024 | Approved | SEAN HAUPT |
| Smoke Detectors | 1/9/2024 | Approved | SEAN HAUPT |
| Final | 1/12/2024 | Corrections Issued | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 1/12/2024 | SGSOV Not Ready | SEAN WIRCH |
| Final | 2/21/2024 | Corrections Issued | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV Not Ready | JOHN KIDWELL |
| Final | 3/8/2024 | Corrections Issued | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 3/8/2024 | SGSOV Approved | JOHN KIDWELL |
| Final | 5/23/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Service/Power Release | 5/24/2024 | Approved | JOHN KIDWELL |
| Final | 6/3/2024 | Corrections Issued | JOHN KIDWELL |
| Final | 6/11/2024 | OK to Issue CofO | JOHN KIDWELL |