5520 N SYLVIA AVE 91356

Certificate Information: 5520 N SYLVIA AVE 91356

Application / Permit
22010-20000-04881
Plan Check / Job No.
B22VN14835
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 24'-0" x 35'-9" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER ENGINEERING.
Permit Issued
Issued on 2/16/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2022 APPLICANT
Assigned to Plan Check Engineer 10/5/2022 JESSE ARELLANO
Corrections Issued 10/6/2022 JESSE ARELLANO
Building Plans Picked Up 10/18/2022 APPLICANT
Plan Check Approved 2/15/2023 MIROOSH KHACHATOORIAN
Issued 2/16/2023 APPLICANT
CofO in Progress 6/11/2024 JOHN KIDWELL
Permit Finaled 6/21/2024 JOHN JANSON
CofO Issued 6/21/2024 JOHN JANSON
Permit Finaled 6/21/2024 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 12/3/2022 RIDWAN HARDY
Construction within easement Cleared 12/3/2022 RIDWAN HARDY
Address approval Cleared 12/6/2022 CARLOS AGUILERA
Low Impact Development Cleared 2/8/2023 ERNEST TSE
Eng Process Fee Ord 176,300 Cleared 2/9/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 2/9/2023 CARLOS AGUILERA
Sewer availability Cleared 2/9/2023 CARLOS AGUILERA
GPI Written Notices Cleared 2/15/2023 JESSE ARELLANO
Grading Pre-Inspection Cleared 2/15/2023 JESSE ARELLANO

Contact Information

Contractor Arbabi Construction Inc; Lic. No.: 514421-B 21426 VELICATA STREET      WOODLAND HILLS, CA 91364
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/23/2023 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 3/3/2023 Not Ready for Inspection DAVID SANDOVAL
Special/Order Compliance 3/3/2023 Partial Inspection MORRIS JACKSON
Footing/Foundation/Slab 3/7/2023 Approved DAVID SANDOVAL
ELECTRICAL-Rough 4/7/2023 Not Ready for Inspection DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 4/7/2023 Approved DAVID SANDOVAL
PLUMBING-Rough 4/7/2023 Approved DAVID SANDOVAL
ELECTRICAL-Rough 4/14/2023 Partial Approval DAVID SANDOVAL
HVAC-Rough 4/14/2023 Corrections Issued DAVID SANDOVAL
HVAC-Rough 4/21/2023 Not Ready for Inspection DAVID SANDOVAL
Pre-Inspection 4/21/2023 Partial Inspection JUSTIN HAWLEY
Insulation 4/27/2023 Approved SEAN HAUPT
Interior/Exterior Lathing 4/27/2023 Approved SEAN HAUPT
Shower Pan 5/17/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 8/1/2023 Approved SEAN HAUPT
Final 8/1/2023 Corrections Issued SEAN HAUPT
Green Building Final 8/1/2023 Not Ready for Inspection SEAN HAUPT
Green Building Rough 8/1/2023 Approved SEAN HAUPT
MERV13>=Final 8/1/2023 Approved SEAN HAUPT
MERV13>=Rough 8/1/2023 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 8/1/2023 SGSOV Not Ready SEAN HAUPT
Service/Power Release 8/1/2023 Not Ready for Inspection SEAN HAUPT
Smoke Detectors 8/1/2023 Not Ready for Inspection SEAN HAUPT
Verify Sprinkler Sign Off 8/1/2023 Approved SEAN HAUPT
Final 1/9/2024 Not Ready for Inspection SEAN HAUPT
Green Building Final 1/9/2024 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 1/9/2024 SGSOV Not Ready SEAN HAUPT
Service/Power Release 1/9/2024 Approved SEAN HAUPT
Smoke Detectors 1/9/2024 Approved SEAN HAUPT
Final 1/12/2024 Corrections Issued SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV Not Ready SEAN WIRCH
Final 2/21/2024 Corrections Issued JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 2/21/2024 SGSOV Not Ready JOHN KIDWELL
Final 3/8/2024 Corrections Issued JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Approved JOHN KIDWELL
Final 5/23/2024 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 5/24/2024 Approved JOHN KIDWELL
Final 6/3/2024 Corrections Issued JOHN KIDWELL
Final 6/11/2024 OK to Issue CofO JOHN KIDWELL