22354 W KINZIE ST 91311

Certificate Information: 22354 W KINZIE ST 91311

Application / Permit
22010-20000-04874
Plan Check / Job No.
B22VN14772
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: NEW DET. ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 7/28/2023
Issuing Office
Current Status
CofO Issued on 8/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 MAHNAZ NOURHASHEMI
Corrections Issued 10/28/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 11/4/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 11/22/2022 MAHNAZ NOURHASHEMI
Plan Check Approved 7/19/2023 MAHNAZ NOURHASHEMI
Issued 7/28/2023 APPLICANT
CofO in Progress 6/25/2025 JEFFREY HARTLINE
Permit Finaled 8/15/2025 JOHN JANSON
CofO Issued 8/15/2025 JOHN JANSON
Permit Finaled 8/15/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/9/2022 CARLOS AGUILERA
Watercourse Cleared 11/9/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/18/2023 CARLOS AGUILERA
Sewer availability Cleared 1/18/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 2/10/2023 RUEL COLE
Low Impact Development Cleared 7/5/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 7/5/2023 CARLOS AGUILERA
GPI Written Notices Cleared 7/28/2023 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 7/28/2023 MAHNAZ NOURHASHEMI

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/8/2023 Corrections Issued JEFFREY HARTLINE
Pre-Inspection 12/8/2023 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 12/13/2023 Corrections Issued JEFFREY HARTLINE
PLUMBING-Rough 12/29/2023 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 1/2/2024 Partial Approval JEFFREY HARTLINE
Underground Mechanical 1/2/2024 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 1/23/2024 Corrections Issued JEFFREY HARTLINE
ELECTRICAL-Rough 1/26/2024 Corrections Issued JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 1/26/2024 Approved JEFFREY HARTLINE
PLUMBING-Rough 1/26/2024 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 2/9/2024 Approved JEFFREY HARTLINE
Green Building Rough 2/9/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 2/9/2024 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 2/9/2024 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 2/9/2024 Approved JEFFREY HARTLINE
Insulation 2/20/2024 Approved HENRY KIM
Special/Order Compliance 2/20/2024 Corrections Issued HENRY KIM
Drywall Nailing 2/27/2024 Approved JEFFREY HARTLINE
HVAC-Rough 2/27/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 2/27/2024 Partial Approval JEFFREY HARTLINE
Shower Pan 2/27/2024 Approved JEFFREY HARTLINE
Final 7/19/2024 Corrections Issued JEFFREY HARTLINE
Footing/Foundation/Slab 7/19/2024 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 7/19/2024 SGSOV Approved JEFFREY HARTLINE
Service/Power Release 7/19/2024 Not Required JEFFREY HARTLINE
Smoke Detectors 7/19/2024 Not Ready for Inspection JEFFREY HARTLINE
Final 9/16/2024 Partial Approval JEFFREY HARTLINE
Smoke Detectors 9/16/2024 Approved JEFFREY HARTLINE
Special/Order Compliance 4/16/2025 Corrections Issued JEFFREY HARTLINE
Final 6/24/2025 OK to Issue CofO JEFFREY HARTLINE