7850 N LEDGE AVE 91352
Certificate Information: 7850 N LEDGE AVE 91352
- Application / Permit
- 22010-20000-04873
- Plan Check / Job No.
- B22VN14769
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW ADU per ordinace LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 4/27/2023
- Issuing Office
- Current Status
- CofO Issued on 12/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | YASHAR EMAMI |
| Corrections Issued | 10/10/2022 | YASHAR EMAMI |
| Quality Review Completed | 10/20/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 3/2/2023 | YASHAR EMAMI |
| Plan Check Approved | 4/20/2023 | YASHAR EMAMI |
| Issued | 4/27/2023 | APPLICANT |
| CofO in Progress | 3/23/2024 | DAVID ANDERSON |
| CofO in Progress | 4/10/2024 | DAVID ANDERSON |
| CofO in Progress | 9/20/2024 | DAVID ANDERSON |
| Permit Finaled | 12/19/2024 | RUBEN SALAS |
| CofO Issued | 12/19/2024 | RUBEN SALAS |
| Permit Finaled | 12/19/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2022 | LEE GUILBEAUX |
| Permit | Cleared | 10/21/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2022 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 11/26/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 12/12/2022 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 12/15/2022 | CARLOS AGUILERA |
| Hold | Cleared | 5/15/2023 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/18/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 5/18/2023 | Partial Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 5/30/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 6/27/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 6/27/2023 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Partial Approval | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 6/27/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 8/9/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/9/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 8/9/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/9/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 8/9/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 8/9/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 8/28/2023 | Corrections Issued | WILLIAM WREN |
| Insulation | 8/28/2023 | Corrections Issued | WILLIAM WREN |
| Drywall Nailing | 8/31/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Insulation | 8/31/2023 | Corrections Issued | DAVID ANDERSON |
| Insulation | 9/1/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 9/5/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 9/29/2023 | SGSOV Not Ready | DAVID ANDERSON |
| Final | 10/4/2023 | Corrections Issued | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 10/4/2023 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 10/4/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 10/4/2023 | Approved | DAVID ANDERSON |
| Final | 3/11/2024 | Conditional Approval | DAVID ANDERSON |
| Service/Power Release | 3/11/2024 | Approved | DAVID ANDERSON |
| Special/Order Compliance | 4/10/2024 | Corrections Issued | DAVID ANDERSON |
| Final | 9/16/2024 | OK to Issue CofO | DAVID ANDERSON |