14855 W CHATSWORTH ST 91345

Certificate Information: 14855 W CHATSWORTH ST 91345

Application / Permit
22010-20000-04826
Plan Check / Job No.
B22VN14609
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 3/28/2023
Issuing Office
Current Status
CofO Issued on 3/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2022 APPLICANT
Assigned to Plan Check Engineer 10/5/2022 MOHAMMAD ESMAILI
Corrections Issued 10/6/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 2/13/2023 MOHAMMAD ESMAILI
Applicant returned to address corrections 3/16/2023 MOHAMMAD ESMAILI
Applicant returned to address corrections 3/16/2023 MOHAMMAD ESMAILI
Applicant returned to address corrections 3/22/2023 PINANK PATEL
Plan Check Approved 3/27/2023 PINANK PATEL
Issued 3/28/2023 APPLICANT
CofO in Progress 12/19/2023 JAVIER RAMOS JR
No Progress 3/13/2024 ROBERT GOLD
CofO in Progress 3/13/2024 ROBERT GOLD
Permit Finaled 3/22/2024 RUBEN SALAS
CofO Issued 3/22/2024 RUBEN SALAS
Permit Finaled 3/22/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/7/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 10/7/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 10/7/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 12/28/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 1/24/2023 DAGOVERTO GUERRERO
Construction near power lines Cleared 3/14/2023 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/25/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 5/24/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 7/6/2023 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 7/6/2023 Not Ready for Inspection JENNIFER RABUCHIN
Underground Mechanical 7/6/2023 Partial Approval JENNIFER RABUCHIN
Verify Sprinkler Sign Off 7/6/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 7/19/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 7/19/2023 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 7/19/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 7/19/2023 Corrections Issued JENNIFER RABUCHIN
Insulation 7/24/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 7/31/2023 No Access for Inspection MISAEL ESPARZA
Drywall Nailing 8/3/2023 Approved RUBEN SALAS
Service/Power Release 8/16/2023 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Final 8/25/2023 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 8/25/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 9/5/2023 Not Ready for Inspection RAUL OLAGI
Interior/Exterior Lathing 9/5/2023 Partial Inspection RAUL OLAGI
Service/Power Release 9/5/2023 Not Ready for Inspection RAUL OLAGI
Interior/Exterior Lathing 9/15/2023 Approved ROBERT GOLD
BUILDING-Rough-Frame 12/13/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 12/13/2023 Corrections Issued JENNIFER RABUCHIN
Final 12/13/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 12/13/2023 Approved JENNIFER RABUCHIN
Green Building Rough 12/13/2023 Approved JENNIFER RABUCHIN
MERV13>=Final 12/13/2023 Corrections Issued JENNIFER RABUCHIN
MERV13>=Rough 12/13/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/13/2023 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 12/13/2023 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 12/13/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 12/18/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 12/18/2023 Approved JAVIER RAMOS JR
Final 12/18/2023 OK to Issue CofO JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/18/2023 Approved JAVIER RAMOS JR
HVAC-Rough 12/18/2023 Approved JAVIER RAMOS JR
MERV13>=Final 12/18/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 12/18/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/18/2023 SGSOV Approved JAVIER RAMOS JR