16002 W BASSETT ST 91406
Certificate Information: 16002 W BASSETT ST 91406
- Application / Permit
- 22010-20000-04825
- Plan Check / Job No.
- B22VN14608
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW 2-STORY ADU (964 SQ. FT.) -Per Ordinance. LAMC 12.22 A 33 C-D
- Permit Issued
- Issued on 9/25/2024
- Issuing Office
- Current Status
- CofO Issued on 11/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | YASHAR EMAMI |
| Corrections Issued | 10/29/2022 | YASHAR EMAMI |
| Quality Review Completed | 11/3/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 2/14/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 2/23/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 4/19/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 8/2/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 8/30/2024 | YASHAR EMAMI |
| Plan Check Approved | 9/16/2024 | YASHAR EMAMI |
| Issued | 9/25/2024 | APPLICANT |
| CofO in Progress | 10/16/2025 | GAREN HAYRAPETYAN |
| CofO Issued | 11/4/2025 | RUBEN SALAS |
| Permit Finaled | 11/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/22/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/22/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 12/3/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 12/15/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 2/2/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez,, Jose Antonio; Lic. No.: C69472 | 3557 E 58TH ST MAYWOOD, CA 90270 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 10/25/2024 | Partial Approval | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 10/25/2024 | Partial Approval | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 11/1/2024 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2024 | Approved | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 11/15/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 12/26/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/26/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Deputy Wood Construction | 1/7/2025 | Conditional Approval | RAUL OLAGI |
| HVAC-Rough | 1/13/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 1/17/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 1/17/2025 | Approved | SALVADOR MARTINEZ |
| Verify Sprinkler Sign Off | 1/17/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 4/2/2025 | Partial Approval | SALVADOR MARTINEZ |
| Insulation | 4/23/2025 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 4/29/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 5/6/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 6/11/2025 | Partial Approval | MATTHEW NELSON |
| Underground Mechanical | 6/11/2025 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/24/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 6/24/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 8/19/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 8/19/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 8/19/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Final | 8/19/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 8/19/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 8/19/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Service/Power Release | 8/19/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 8/19/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 10/16/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 10/16/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| HVAC-Final | 10/16/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Final | 10/16/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 10/16/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 10/16/2025 | Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 10/16/2025 | Approved | GAREN HAYRAPETYAN |