5325 N QUAKERTOWN AVE 91364

Certificate Information: 5325 N QUAKERTOWN AVE 91364

Application / Permit
22010-20000-04813
Plan Check / Job No.
B22VN14558
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. NEW 2-STORY SFD WITH ATTACHED 2-CAR GARAGE
Permit Issued
Issued on 2/14/2023
Issuing Office
Current Status
CofO Issued on 4/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 MAHNAZ NOURHASHEMI
Corrections Issued 10/14/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 10/25/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 2/13/2023 MAHNAZ NOURHASHEMI
Issued 2/14/2023 APPLICANT
CofO in Progress 3/21/2024 MORRIS JACKSON
Permit Finaled 4/1/2024 JOHN JANSON
CofO Issued 4/1/2024 JOHN JANSON
Permit Finaled 4/1/2024 JOHN JANSON

Permit Application Clearance Information

GPI Written Notices Cleared 10/12/2022 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 10/12/2022 MAHNAZ NOURHASHEMI
Permit Cleared 11/1/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 11/2/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 11/2/2022 JOSE DUARTE-DIAZ
Hydrant and Access approval Cleared 12/13/2022 GILBERT URREA
Low Impact Development Cleared 1/17/2023 CHRIS VONG
Roof/Waste drainage to street Cleared 1/18/2023 RYAN KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/16/2023 Not Ready for Inspection PETER FOLLING
Pre-Inspection 4/21/2023 Approved PETER FOLLING
Footing/Foundation/Slab 5/10/2023 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 5/10/2023 Corrections Issued PETER FOLLING
PLUMBING-Rough 5/15/2023 Approved PETER FOLLING
Footing/Foundation/Slab 5/24/2023 Approved PETER FOLLING
BUILDING-Rough-Frame 6/5/2023 Corrections Issued PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 6/5/2023 Partial Approval PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Approved PETER FOLLING
Verify Sprinkler Sign Off 6/20/2023 Not Ready for Inspection PETER FOLLING
HVAC-Rough 6/26/2023 Corrections Issued PETER FOLLING
ELECTRICAL-Rough 7/7/2023 Approved PETER FOLLING
HVAC-Rough 7/7/2023 Approved PETER FOLLING
PLUMBING-Rough 7/12/2023 Approved PETER FOLLING
BUILDING-Rough-Frame 7/25/2023 Approved PETER FOLLING
Green Building Rough 7/25/2023 Approved PETER FOLLING
Interior/Exterior Lathing 7/25/2023 Approved PETER FOLLING
Shower Pan 7/25/2023 Approved PETER FOLLING
Verify Sprinkler Sign Off 7/25/2023 Approved PETER FOLLING
Insulation 8/15/2023 Corrections Issued PETER FOLLING
Insulation 8/17/2023 Approved PETER FOLLING
Interior/Exterior Lathing 8/17/2023 Approved PETER FOLLING
Drywall Nailing 9/7/2023 Approved PETER FOLLING
Gas Test 2/21/2024 Approved MORRIS JACKSON
Final 3/14/2024 Corrections Issued MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 3/14/2024 SGSOV Not Ready MORRIS JACKSON
Service/Power Release 3/14/2024 Not Ready for Inspection MORRIS JACKSON
Smoke Detectors 3/14/2024 Corrections Issued MORRIS JACKSON
Deputy Reinf. Concrete 3/20/2024 Conditional Approval MORRIS JACKSON
Final 3/20/2024 OK to Issue CofO MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 3/20/2024 SGSOV Approved MORRIS JACKSON
Service/Power Release 3/20/2024 Approved MORRIS JACKSON
Smoke Detectors 3/20/2024 Approved MORRIS JACKSON