10300 W ARNWOOD ROAD 91342

Certificate Information: 10300 W ARNWOOD ROAD 91342

Application / Permit
22010-20000-04781
Plan Check / Job No.
B22VN14427
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan NEW 23'-6" X 32' IRREGULAR SHAPED 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/10/2023
Issuing Office
Current Status
CofO Issued on 12/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2022 APPLICANT
Assigned to Plan Check Engineer 9/29/2022 RAPHAEL ROSAS
Corrections Issued 10/4/2022 RAPHAEL ROSAS
Quality Review Completed 10/5/2022 STEVEN KIM
Applicant returned to address corrections 7/5/2023 RAPHAEL ROSAS
Plan Check Approved 8/9/2023 RAPHAEL ROSAS
Issued 8/10/2023 APPLICANT
CofO in Progress 12/30/2025 JACK KARGODORIAN
Permit Finaled 12/31/2025 RUBEN SALAS
CofO Issued 12/31/2025 RUBEN SALAS
Permit Finaled 12/31/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/12/2022 ROMAN GUTIERREZ
Miscellaneous Cleared 10/12/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 10/13/2022 ROMAN GUTIERREZ
Low Impact Development Cleared 10/19/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 10/19/2022 ROMAN GUTIERREZ
Specific Plan Cleared 10/21/2022 SARAH HOUNSELL
ZI Cleared 10/21/2022 SARAH HOUNSELL
Private sewage disp. approval Cleared 2/1/2023 KIRK LINKLATER
Grading Pre-Inspection Cleared 6/23/2023 VASIL MIHALEV
GPI Written Notices Cleared 8/9/2023 RAPHAEL ROSAS

Contact Information

Architect Isagholi,, Armen; Lic. No.: NA33577       ,
Contractor Owner-Builder       ,
Engineer Karapetian,, Arbi; Lic. No.: C79953 6854 FOOTHILL BLVD      TUJUNGA, CA 91042

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/15/2023 Partial Inspection WILLIAM WREN
Excavation/Setback/Form/Re-Bar 9/28/2023 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 9/28/2023 Corrections Issued WILLIAM WREN
Deputy Reinf. Concrete 10/3/2023 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 10/11/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 10/20/2023 Partial Approval WILLIAM WREN
Green Building Rough 10/20/2023 Not Ready for Inspection WILLIAM WREN
MERV13>=Rough 10/20/2023 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 10/20/2023 Partial Approval WILLIAM WREN
Verify Sprinkler Sign Off 10/20/2023 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Partial Approval WILLIAM WREN
Insulation 10/26/2023 Partial Approval WILLIAM WREN
Sewer 10/26/2023 Approved WILLIAM WREN
Deputy Wood Construction 1/9/2024 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 1/12/2024 Not Ready for Inspection WILLIAM WREN
Green Building Rough 1/12/2024 Not Ready for Inspection WILLIAM WREN
HVAC-Rough 1/12/2024 Corrections Issued WILLIAM WREN
MERV13>=Rough 1/12/2024 Not Ready for Inspection WILLIAM WREN
Verify Sprinkler Sign Off 1/12/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 1/25/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 1/25/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 1/25/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 1/25/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 1/25/2024 Corrections Issued CHRISTOPHER ROJAS
MERV13>=Rough 1/25/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 1/25/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 1/31/2024 Corrections Issued CRAIG DAVIS
HVAC-Rough 1/31/2024 Corrections Issued CRAIG DAVIS
Wood Frame 1/31/2024 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 2/2/2024 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 2/2/2024 Approved MATTHEW NELSON
Green Building Rough 2/2/2024 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 2/2/2024 Approved MATTHEW NELSON
MERV13>=Rough 2/2/2024 Not Ready for Inspection MATTHEW NELSON
Wood Frame 2/2/2024 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 2/14/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 2/14/2024 Approved WILLIAM WREN
Green Building Rough 2/14/2024 Approved WILLIAM WREN
MERV13>=Rough 2/14/2024 Approved WILLIAM WREN
Interior/Exterior Lathing 2/27/2024 Partial Approval WILLIAM WREN
Interior/Exterior Lathing 3/7/2024 Partial Approval WILLIAM WREN
Insulation 4/3/2024 Approved WILLIAM WREN
Shower Pan 4/3/2024 Approved WILLIAM WREN
Drywall Nailing 4/9/2024 Approved WILLIAM WREN
Underground Mechanical 8/12/2024 Approved WILLIAM WREN
Final 10/31/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 10/31/2025 Approved KEVIN BERBERYAN
Green Building Final 10/31/2025 Approved KEVIN BERBERYAN
MERV13>=Final 10/31/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 10/31/2025 Not Required KEVIN BERBERYAN
Smoke Detectors 10/31/2025 Approved KEVIN BERBERYAN
Final 11/20/2025 Corrections Issued NICHOLAS TROWBRIDGE
Final 12/24/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 12/29/2025 OK to Issue CofO JACK KARGODORIAN