11569 W GILMORE ST 91606

Certificate Information: 11569 W GILMORE ST 91606

Application / Permit
22010-20000-04775
Plan Check / Job No.
B22VN14409
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADU (1188 SF) PER LAMC 12.22A.33(c)-(e) AND (8 SF) ADDITION TO (E) 1-STORY STORAGE BUILDING
Permit Issued
Issued on 1/12/2023
Issuing Office
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2022 APPLICANT
Assigned to Plan Check Engineer 9/29/2022 JOE VO
Corrections Issued 9/30/2022 VIVIAN LAO
Plan Check Approved 1/2/2023 JOE VO
Issued 1/12/2023 APPLICANT
CofO in Progress 10/13/2023 JOHN HAYES
Permit Finaled 4/3/2024 RUBEN SALAS
CofO Issued 4/3/2024 RUBEN SALAS
Permit Finaled 4/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/4/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/4/2022 JEANIE LAM
Highway dedication Cleared 10/4/2022 JEANIE LAM
Sewer availability Cleared 10/4/2022 JEANIE LAM
Low Impact Development Cleared 12/12/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 12/13/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/16/2023 Partial Approval JACK KARGODORIAN
Underground Mechanical 6/16/2023 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 6/20/2023 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 7/14/2023 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 7/25/2023 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 7/25/2023 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 7/25/2023 Approved JOHN HAYES
HVAC-Rough 7/25/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 7/25/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 7/26/2023 Partial Inspection JENNIFER RABUCHIN
Green Building Rough 7/26/2023 Not Ready for Inspection JENNIFER RABUCHIN
Wood Frame 7/26/2023 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 7/31/2023 Approved JOHN HAYES
HVAC-Rough 7/31/2023 Corrections Issued JOHN HAYES
Interior/Exterior Lathing 7/31/2023 Partial Approval JOHN HAYES
PLUMBING-Rough 7/31/2023 Approved JOHN HAYES
HVAC-Rough 8/4/2023 Approved JOHN HAYES
Insulation 8/4/2023 Approved JOHN HAYES
Shower Pan 8/4/2023 Approved JOHN HAYES
Drywall Nailing 8/14/2023 Approved JACK KARGODORIAN
Green Building Rough 8/14/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 8/14/2023 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 9/26/2023 Approved JOHN HAYES
ELECTRICAL-Final 9/26/2023 Approved JOHN HAYES
Final 9/26/2023 Corrections Issued JOHN HAYES
Green Building Final 9/26/2023 Approved JOHN HAYES
HVAC-Final 9/26/2023 Approved JOHN HAYES
PLUMBING-Final 9/26/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 9/26/2023 SGSOV Approved JOHN HAYES
Service/Power Release 9/26/2023 Not Ready for Inspection JOHN HAYES
Smoke Detectors 9/26/2023 Approved JOHN HAYES
Final 10/5/2023 Corrections Issued JOHN HAYES
Service/Power Release 10/5/2023 Not Ready for Inspection JOHN HAYES
Final 10/11/2023 OK to Issue CofO JOHN HAYES
Service/Power Release 10/11/2023 Approved JOHN HAYES
Special/Order Compliance 11/29/2023 Corrections Issued JOHN HAYES