1340 S BECKWITH AVE 90049

Certificate Information: 1340 S BECKWITH AVE 90049

Application / Permit
22010-20000-04761
Plan Check / Job No.
B22VN14390
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 59'-9" x 78'-11" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE, BASEMENT, AND OPEN TRELLIS; NFPA-13D THRU-OUT
Permit Issued
Issued on 5/12/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2022 APPLICANT
Assigned to Plan Check Engineer 9/29/2022 SEAN SHAHMIRI
Corrections Issued 10/3/2022 SEAN SHAHMIRI
Quality Review Completed 10/4/2022 OMID HEDAYAT
Building Plans Picked Up 10/6/2022 APPLICANT
Plan Check Approved 1/10/2023 SEAN SHAHMIRI
Issued 5/12/2023 APPLICANT
CofO in Progress 9/12/2025 HERBERT GIRON
Permit Finaled 9/12/2025 RICHARD STEINBACH
CofO Issued 9/12/2025 RICHARD STEINBACH
Permit Finaled 9/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

Trees in Parkway Cleared 10/7/2022 ADALBERTO VERA
Address approval Cleared 10/11/2022 CATHERINE ADROVER
Permit Cleared 10/11/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 10/13/2022 CATHERINE ADROVER
Sewer availability Cleared 10/13/2022 CATHERINE ADROVER
Hydrant and Access approval Cleared 11/10/2022 LAVEON RIDER
Low Impact Development Cleared 12/29/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 1/5/2023 DINAH GARIN

Contact Information

Contractor Wpic Construction Llc; Lic. No.: 1029691-B 125 W MAPLE AVE      MONROVIA, CA 91016
Engineer Dermendjian,, Raffi Hrag; Lic. No.: C88261 9325 SHOSHONE AVENUE      NORTHRIDGE, CA 91325
Engineer Labib,, Youhanna T.; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/5/2023 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 7/11/2023 Partial Approval HERBERT GIRON
Pre-Inspection 7/18/2023 Corrections Issued MICHAEL PELHAM
Underground Mechanical 7/20/2023 Partial Approval KENNETH NAGLE
Underground Mechanical 7/21/2023 No Access for Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 7/31/2023 Partial Inspection OGANES TARAKHCHYAN
Deputy Reinf. Concrete 8/7/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 8/15/2023 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 8/15/2023 Corrections Issued ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 8/16/2023 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 8/17/2023 Partial Approval KENNETH NAGLE
Deputy Reinf. Concrete 8/18/2023 No Access for Inspection KENNETH NAGLE
Deputy Reinf. Concrete 8/23/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 8/29/2023 No Access for Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 8/30/2023 Partial Approval ARAM AVEDISIAN
Deputy Reinf. Concrete 9/8/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 9/14/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 9/21/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 9/25/2023 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 9/25/2023 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 9/27/2023 No Access for Inspection KENNETH NAGLE
Deputy Reinf. Concrete 9/28/2023 No Access for Inspection KENNETH NAGLE
Deputy Steel/Welding 10/19/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 10/23/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 10/24/2023 No Access for Inspection KENNETH NAGLE
Deputy Steel/Welding 10/30/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 10/31/2023 Approved OGANES TARAKHCHYAN
Structural Steel Frame 10/31/2023 Partial Inspection OGANES TARAKHCHYAN
Underground Mechanical 11/6/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 11/7/2023 Partial Approval ARAM AVEDISIAN
Deputy Steel/Welding 11/8/2023 Conditional Approval ARAM AVEDISIAN
Deputy Wood Construction 11/14/2023 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Partial Approval ARAM AVEDISIAN
Structural Steel Frame 11/17/2023 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 11/29/2023 Partial Approval ARAM AVEDISIAN
Deputy Reinf. Concrete 11/30/2023 Conditional Approval ARAM AVEDISIAN
Deputy Wood Construction 12/19/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 12/27/2023 Corrections Issued KEVIN SARGSYAN
Deputy Reinf. Concrete 1/18/2024 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 2/16/2024 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Partial Inspection KENNETH NAGLE
Deputy Wood Construction 3/20/2024 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 4/3/2024 No Access for Inspection KENNETH NAGLE
Deputy Wood Construction 4/4/2024 Approved ARAM AVEDISIAN
Final 4/4/2024 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 4/4/2024 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 4/10/2024 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 4/15/2024 Approved JESUS RODRIGUEZ
Deputy Wood Construction 4/18/2024 Conditional Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 5/8/2024 Conditional Approval CARLOS MATAMOROS
Deputy Drilled-In Anchors 5/9/2024 Conditional Approval MICHAEL PELHAM
Pre-Inspection 5/22/2024 Partial Inspection ARAM AVEDISIAN
Interior/Exterior Lathing 7/11/2024 Partial Approval ARAM AVEDISIAN
HVAC-Rough 8/9/2024 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 8/13/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 8/13/2024 Approved JESUS RODRIGUEZ
Green Building Rough 8/13/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 8/13/2024 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 8/13/2024 Approved JESUS RODRIGUEZ
Insulation 8/23/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/26/2024 Not Ready for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 8/29/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 9/6/2024 Approved JESUS RODRIGUEZ
Special/Order Compliance 9/6/2024 Partial Inspection MICHAEL ALLEN
ELECTRICAL-Rough 9/13/2024 Not Ready for Inspection JESUS RODRIGUEZ
Shower Pan 10/22/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 10/25/2024 Approved EVAN COOPER
Shower Pan 10/25/2024 Approved EVAN COOPER
Underground Mechanical 12/10/2024 Corrections Issued JESUS RODRIGUEZ
Underground Mechanical 12/13/2024 Partial Approval JESUS RODRIGUEZ
Underground Mechanical 12/18/2024 Order to Comply Issued KENNETH NAGLE
Underground Mechanical 12/19/2024 Conditional Approval JESUS RODRIGUEZ
Underground Mechanical 12/30/2024 Partial Approval JESUS RODRIGUEZ
Sewer 1/21/2025 Approved JESUS RODRIGUEZ
Underground Mechanical 2/18/2025 Approved JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/27/2025 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 2/27/2025 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 3/28/2025 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 4/10/2025 Corrections Issued HERBERT GIRON
Smoke Detectors 4/10/2025 Partial Approval HERBERT GIRON
ELECTRICAL-Final 4/11/2025 Approved HERBERT GIRON
Service/Power Release 4/14/2025 Approved KENNETH NAGLE
Piling/Pier/Caisson 5/12/2025 Corrections Issued HERBERT GIRON
PLUMBING-Final 5/20/2025 Corrections Issued HERBERT GIRON
Gas Test 5/28/2025 Not Ready for Inspection HERBERT GIRON
Gas Test 6/3/2025 Approved HERBERT GIRON
HVAC-Final 6/5/2025 Corrections Issued HERBERT GIRON
PLUMBING-Final 6/5/2025 Approved HERBERT GIRON
HVAC-Final 6/6/2025 Approved KEVIN SARGSYAN
Deputy Drilled-In Anchors 7/18/2025 Conditional Approval HERBERT GIRON
Deputy Drilled-In Anchors 8/19/2025 Conditional Approval HERBERT GIRON
Final 8/22/2025 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 8/22/2025 Approved HERBERT GIRON
Green Building Final 8/22/2025 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/22/2025 SGSOV Not Ready HERBERT GIRON
Smoke Detectors 8/22/2025 Approved HERBERT GIRON
Special/Order Compliance 8/22/2025 Partial Inspection JAYLIN GRAVITTE
Structural Steel Frame 8/22/2025 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 9/3/2025 SGSOV Approved HERBERT GIRON
Final 9/5/2025 Corrections Issued HERBERT GIRON
Final 9/12/2025 OK to Issue CofO HERBERT GIRON