1340 S BECKWITH AVE 90049
Certificate Information: 1340 S BECKWITH AVE 90049
- Application / Permit
- 22010-20000-04761
- Plan Check / Job No.
- B22VN14390
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 59'-9" x 78'-11" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE, BASEMENT, AND OPEN TRELLIS; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 5/12/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | SEAN SHAHMIRI |
| Corrections Issued | 10/3/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 10/4/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 10/6/2022 | APPLICANT |
| Plan Check Approved | 1/10/2023 | SEAN SHAHMIRI |
| Issued | 5/12/2023 | APPLICANT |
| CofO in Progress | 9/12/2025 | HERBERT GIRON |
| Permit Finaled | 9/12/2025 | RICHARD STEINBACH |
| CofO Issued | 9/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 10/7/2022 | ADALBERTO VERA |
| Address approval | Cleared | 10/11/2022 | CATHERINE ADROVER |
| Permit | Cleared | 10/11/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 10/13/2022 | CATHERINE ADROVER |
| Hydrant and Access approval | Cleared | 11/10/2022 | LAVEON RIDER |
| Low Impact Development | Cleared | 12/29/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 1/5/2023 | DINAH GARIN |
Contact Information
| Contractor | Wpic Construction Llc; Lic. No.: 1029691-B | 125 W MAPLE AVE MONROVIA, CA 91016 |
| Engineer | Dermendjian,, Raffi Hrag; Lic. No.: C88261 | 9325 SHOSHONE AVENUE NORTHRIDGE, CA 91325 |
| Engineer | Labib,, Youhanna T.; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/5/2023 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/11/2023 | Partial Approval | HERBERT GIRON |
| Pre-Inspection | 7/18/2023 | Corrections Issued | MICHAEL PELHAM |
| Underground Mechanical | 7/20/2023 | Partial Approval | KENNETH NAGLE |
| Underground Mechanical | 7/21/2023 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 7/31/2023 | Partial Inspection | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 8/7/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 8/15/2023 | No Access for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 8/15/2023 | Corrections Issued | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 8/16/2023 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 8/17/2023 | Partial Approval | KENNETH NAGLE |
| Deputy Reinf. Concrete | 8/18/2023 | No Access for Inspection | KENNETH NAGLE |
| Deputy Reinf. Concrete | 8/23/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 8/29/2023 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 8/30/2023 | Partial Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 9/8/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 9/14/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 9/21/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 9/25/2023 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 9/25/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 9/27/2023 | No Access for Inspection | KENNETH NAGLE |
| Deputy Reinf. Concrete | 9/28/2023 | No Access for Inspection | KENNETH NAGLE |
| Deputy Steel/Welding | 10/19/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 10/23/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 10/24/2023 | No Access for Inspection | KENNETH NAGLE |
| Deputy Steel/Welding | 10/30/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 10/31/2023 | Approved | OGANES TARAKHCHYAN |
| Structural Steel Frame | 10/31/2023 | Partial Inspection | OGANES TARAKHCHYAN |
| Underground Mechanical | 11/6/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/7/2023 | Partial Approval | ARAM AVEDISIAN |
| Deputy Steel/Welding | 11/8/2023 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 11/14/2023 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2023 | Partial Approval | ARAM AVEDISIAN |
| Structural Steel Frame | 11/17/2023 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 11/29/2023 | Partial Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 11/30/2023 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 12/19/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2023 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 1/18/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 2/16/2024 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | Partial Inspection | KENNETH NAGLE |
| Deputy Wood Construction | 3/20/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 4/3/2024 | No Access for Inspection | KENNETH NAGLE |
| Deputy Wood Construction | 4/4/2024 | Approved | ARAM AVEDISIAN |
| Final | 4/4/2024 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/10/2024 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/15/2024 | Approved | JESUS RODRIGUEZ |
| Deputy Wood Construction | 4/18/2024 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 5/8/2024 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 5/9/2024 | Conditional Approval | MICHAEL PELHAM |
| Pre-Inspection | 5/22/2024 | Partial Inspection | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/11/2024 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 8/9/2024 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/13/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/13/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 8/13/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 8/13/2024 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 8/13/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 8/23/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/26/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/29/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 9/6/2024 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 9/6/2024 | Partial Inspection | MICHAEL ALLEN |
| ELECTRICAL-Rough | 9/13/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Shower Pan | 10/22/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 10/25/2024 | Approved | EVAN COOPER |
| Shower Pan | 10/25/2024 | Approved | EVAN COOPER |
| Underground Mechanical | 12/10/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Underground Mechanical | 12/13/2024 | Partial Approval | JESUS RODRIGUEZ |
| Underground Mechanical | 12/18/2024 | Order to Comply Issued | KENNETH NAGLE |
| Underground Mechanical | 12/19/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Underground Mechanical | 12/30/2024 | Partial Approval | JESUS RODRIGUEZ |
| Sewer | 1/21/2025 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 2/18/2025 | Approved | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 2/27/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 2/27/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 3/28/2025 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 4/10/2025 | Corrections Issued | HERBERT GIRON |
| Smoke Detectors | 4/10/2025 | Partial Approval | HERBERT GIRON |
| ELECTRICAL-Final | 4/11/2025 | Approved | HERBERT GIRON |
| Service/Power Release | 4/14/2025 | Approved | KENNETH NAGLE |
| Piling/Pier/Caisson | 5/12/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 5/20/2025 | Corrections Issued | HERBERT GIRON |
| Gas Test | 5/28/2025 | Not Ready for Inspection | HERBERT GIRON |
| Gas Test | 6/3/2025 | Approved | HERBERT GIRON |
| HVAC-Final | 6/5/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 6/5/2025 | Approved | HERBERT GIRON |
| HVAC-Final | 6/6/2025 | Approved | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 7/18/2025 | Conditional Approval | HERBERT GIRON |
| Deputy Drilled-In Anchors | 8/19/2025 | Conditional Approval | HERBERT GIRON |
| Final | 8/22/2025 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 8/22/2025 | Approved | HERBERT GIRON |
| Green Building Final | 8/22/2025 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 8/22/2025 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 8/22/2025 | Approved | HERBERT GIRON |
| Special/Order Compliance | 8/22/2025 | Partial Inspection | JAYLIN GRAVITTE |
| Structural Steel Frame | 8/22/2025 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 9/3/2025 | SGSOV Approved | HERBERT GIRON |
| Final | 9/5/2025 | Corrections Issued | HERBERT GIRON |
| Final | 9/12/2025 | OK to Issue CofO | HERBERT GIRON |