523-525 W 62ND ST 90044

Certificate Information: 523-525 W 62ND ST 90044

Application / Permit
22010-20000-04738
Plan Check / Job No.
B22VN14317
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan NEW 2 STORY DUPLEX W ATTACHED 3 CAR GARAGE
Permit Issued
Issued on 3/6/2023
Issuing Office
Current Status
CofO Issued on 9/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2022 APPLICANT
Assigned to Plan Check Engineer 9/29/2022 STARR CHEN
Corrections Issued 10/4/2022 STARR CHEN
Quality Review Completed 10/4/2022 EUGENE BARBEAU
Plan Check Approved 1/30/2023 TSE MING HUANG
Issued 3/6/2023 APPLICANT
CofO in Progress 8/30/2023 ALEJANDRO DE ARTOLA
Permit Finaled 9/13/2023 DEROLD HAUFF
CofO Issued 9/13/2023 DEROLD HAUFF
Permit Finaled 9/13/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/13/2022 WALLIE JONG
CPC Cleared 10/13/2022 SPENCER WEJROWSKI
CPC Cleared 10/13/2022 SPENCER WEJROWSKI
Frnt yard landscape/Water mgmt Cleared 10/13/2022 SPENCER WEJROWSKI
Miscellaneous Cleared 10/13/2022 SPENCER WEJROWSKI
Permit Cleared 10/13/2022 WALLIE JONG
Trees in Parkway Cleared 10/14/2022 ADALBERTO VERA
Eng Process Fee Ord 176,300 Cleared 10/18/2022 THAN WIN
Sewer availability Cleared 10/21/2022 WALLIE JONG
Hydrant and Access approval Cleared 11/5/2022 RUEL COLE
Low Impact Development Cleared 12/1/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 12/1/2022 WALLIE JONG
SB8 RUD Cleared 12/27/2022 JAMES MCCARTHY

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/12/2023 Approved BRENDAN MORELLI
Footing/Foundation/Slab 4/12/2023 Approved BRENDAN MORELLI
Deputy Reinf. Concrete 4/13/2023 Conditional Approval BRENDAN MORELLI
BUILDING-Rough-Frame 4/25/2023 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 4/25/2023 Partial Approval BRENDAN MORELLI
Sewer 4/25/2023 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 4/27/2023 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 4/27/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/28/2023 Partial Approval ALEJANDRO DE ARTOLA
Pre-Inspection 4/28/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/8/2023 Partial Approval BRENDAN MORELLI
Deputy Wood Construction 5/18/2023 Conditional Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 5/19/2023 Approved BRENDAN MORELLI
HVAC-Rough 6/5/2023 Conditional Approval BRENDAN MORELLI
PLUMBING-Rough 6/5/2023 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 6/6/2023 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 6/6/2023 Approved BRENDAN MORELLI
HVAC-Rough 6/6/2023 Approved BRENDAN MORELLI
MERV13>=Rough 6/6/2023 Approved BRENDAN MORELLI
PLUMBING-Rough 6/6/2023 Approved BRENDAN MORELLI
Verify Sprinkler Sign Off 6/6/2023 Approved BRENDAN MORELLI
Insulation 6/16/2023 Approved RUBEN SALAS
Drywall Nailing 6/22/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 6/22/2023 Partial Approval BRENDAN MORELLI
Interior/Exterior Lathing 7/10/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 7/27/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/1/2023 Partial Approval ALEJANDRO DE ARTOLA
Final 8/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 8/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 8/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 8/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/28/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/28/2023 Approved ALEJANDRO DE ARTOLA
Gas Test 8/28/2023 Approved ALEJANDRO DE ARTOLA
MERV13>=Final 8/28/2023 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 8/28/2023 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/28/2023 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 8/28/2023 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 8/28/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/29/2023 Approved ALEJANDRO DE ARTOLA
Final 8/29/2023 OK to Issue CofO ALEJANDRO DE ARTOLA
HVAC-Final 8/29/2023 Approved ALEJANDRO DE ARTOLA
Service/Power Release 8/29/2023 Approved ALEJANDRO DE ARTOLA