11645 N GLADSTONE AVE 91342

Certificate Information: 11645 N GLADSTONE AVE 91342

Application / Permit
22010-20000-04737
Plan Check / Job No.
B22VN14305
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 16'-6" x 36'-4" DETACHED TWO-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 3/8/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/22/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 SEAN SHAHMIRI
Corrections Issued 10/17/2022 SEAN SHAHMIRI
Quality Review Completed 10/19/2022 OMID HEDAYAT
Building Plans Picked Up 10/21/2022 APPLICANT
Plan Check Approved 2/21/2023 SEAN SHAHMIRI
Issued 3/8/2023 APPLICANT
CofO in Progress 6/12/2024 MICHEL ABAJAN
CofO in Progress 6/24/2024 ROBERT GOLD
No Progress 6/25/2024 MICHEL ABAJAN
CofO in Progress 8/30/2024 ROBERT GOLD
CofO in Progress 8/30/2024 ROBERT GOLD
Permit Finaled 9/5/2024 DANIEL ORRANTE
CofO Issued 9/5/2024 DANIEL ORRANTE
Permit Finaled 9/5/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/26/2022 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 11/8/2022 FERNANDO GIL
Sewer availability Cleared 11/8/2022 FERNANDO GIL
Hydrant and Access approval Cleared 11/11/2022 JOHN CONNEALLY
Low Impact Development Cleared 1/24/2023 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 1/26/2023 FERNANDO GIL
SB8 RUD Cleared 1/30/2023 JESSICA WANG
Construction near power lines Cleared 2/10/2023 WALTER RAMIREZ
Grading Pre-Inspection Cleared 2/21/2023 SEAN SHAHMIRI

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/31/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 6/23/2023 Not Ready for Inspection MICHEL ABAJAN
Underground Mechanical 6/29/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/24/2023 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/7/2023 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 8/30/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 8/30/2023 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 8/30/2023 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 9/11/2023 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 9/11/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/11/2023 Partial Approval MICHEL ABAJAN
Green Building Rough 9/11/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 9/11/2023 Corrections Issued MICHEL ABAJAN
MERV13>=Rough 9/11/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 9/11/2023 Not Ready for Inspection MICHEL ABAJAN
Verify Sprinkler Sign Off 9/11/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 10/3/2023 Approved MICHEL ABAJAN
Green Building Rough 10/3/2023 Approved MICHEL ABAJAN
HVAC-Final 10/3/2023 Approved MICHEL ABAJAN
PLUMBING-Final 10/3/2023 Approved MICHEL ABAJAN
Insulation 10/6/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/6/2023 Approved MICHEL ABAJAN
Drywall Nailing 10/16/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/16/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/25/2024 Approved MICHEL ABAJAN
Final 1/25/2024 Corrections Issued MICHEL ABAJAN
Green Building Final 1/25/2024 Approved MICHEL ABAJAN
MERV13>=Final 1/25/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/25/2024 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 1/25/2024 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 1/25/2024 Approved MICHEL ABAJAN
Final 3/1/2024 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/1/2024 SGSOV Approved MICHEL ABAJAN
Service/Power Release 3/1/2024 Approved MICHEL ABAJAN
Final 6/12/2024 OK to Issue CofO MICHEL ABAJAN