9526 N GEYSER AVE 91324
Certificate Information: 9526 N GEYSER AVE 91324
- Application / Permit
- 22010-20000-04736
- Plan Check / Job No.
- B22VN14303
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- (N) Detached covered patio.
- Permit Issued
- Issued on 11/9/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2022 | RAMA DABADGE |
| Corrections Issued | 9/26/2022 | RAMA DABADGE |
| Building Plans Picked Up | 9/28/2022 | APPLICANT |
| Plan Check Approved | 11/9/2022 | RAMA DABADGE |
| Issued | 11/9/2022 | APPLICANT |
| CofO in Progress | 4/4/2023 | DAVID SCANTLIN |
| Permit Finaled | 1/31/2024 | JOHN JANSON |
| CofO Issued | 1/31/2024 | JOHN JANSON |
| Permit Finaled | 1/31/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 10/12/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mniarji,, Majd Sameer; Lic. No.: C93049 | 7812 VASSAR AVENUE CANOGA PARK, CA 91304 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/28/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 12/30/2022 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 12/30/2022 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2022 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 12/30/2022 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 4/3/2023 | Approved | DAVID SCANTLIN |
| Final | 4/3/2023 | OK to Issue CofO | DAVID SCANTLIN |
| HVAC-Final | 4/3/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 4/3/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 4/3/2023 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 4/3/2023 | Approved | DAVID SCANTLIN |
| Smoke Detectors | 4/3/2023 | Approved | DAVID SCANTLIN |