16828 W OTSEGO ST 91436

Certificate Information: 16828 W OTSEGO ST 91436

Application / Permit
22010-20000-04707
Plan Check / Job No.
B22VN14244
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 40'-4" x 20'-8" IRREGULAR SHAPED FULLY SPRINKLERED DEATCHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c) , (d), and (g)
Permit Issued
Issued on 5/10/2023
Issuing Office
Current Status
CofO Issued on 10/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2022 APPLICANT
Assigned to Plan Check Engineer 9/23/2022 ARTIN ZARUKIAN
Corrections Issued 9/24/2022 ARTIN ZARUKIAN
Building Plans Picked Up 12/12/2022 APPLICANT
Plan Check Approved 2/8/2023 SARKIS HARABEDIAN
Issued 5/10/2023 APPLICANT
Permit Finaled 10/4/2025 MICHAEL PELHAM
CofO Issued 10/4/2025 MICHAEL PELHAM
Permit Finaled 10/4/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 10/12/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 10/12/2022 MEGAN GODINEZ
Sewer availability Cleared 10/12/2022 MEGAN GODINEZ
Low Impact Development Cleared 10/24/2022 ANTHONY VARGAS
Hydrant and Access approval Cleared 11/15/2022 LAVEON RIDER
Construction near power lines Cleared 12/6/2022 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 12/7/2022 MEGAN GODINEZ

Contact Information

Contractor Nork Construction Inc; Lic. No.: 1058592-B 17204 CHATSWORTH ST #10      GRANADA HILLS, CA 91344
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/13/2023 Partial Approval VINCENT HANLEY
Sewer 7/13/2023 Approved VINCENT HANLEY
Footing/Foundation/Slab 7/17/2023 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 7/27/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/20/2023 Partial Approval VINCENT HANLEY
Wood Frame 9/20/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Not Ready for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 10/12/2023 Approved VINCENT HANLEY
HVAC-Rough 10/12/2023 Approved VINCENT HANLEY
PLUMBING-Rough 10/12/2023 Approved VINCENT HANLEY
Sewer 10/12/2023 Approved VINCENT HANLEY
ELECTRICAL-Rough 10/20/2023 Approved VINCENT HANLEY
Shower Pan 11/14/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 11/27/2023 Approved VINCENT HANLEY
Green Building Rough 11/27/2023 Approved VINCENT HANLEY
Insulation 11/27/2023 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 11/27/2023 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 11/27/2023 Approved VINCENT HANLEY
Wood Frame 11/27/2023 Approved VINCENT HANLEY
Insulation 12/6/2023 Approved VINCENT HANLEY
Drywall Nailing 12/12/2023 Approved VINCENT HANLEY
ELECTRICAL-Final 5/31/2024 Conditional Approval THOMAS FINNILA
HVAC-Final 6/4/2024 Approved THOMAS FINNILA
PLUMBING-Final 6/7/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 7/29/2024 Not Ready for Inspection THOMAS FINNILA
Final 7/29/2024 Not Ready for Inspection THOMAS FINNILA
Green Building Final 7/29/2024 Approved THOMAS FINNILA
PLUMBING-Final 7/29/2024 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Approved THOMAS FINNILA
Service/Power Release 7/29/2024 Approved THOMAS FINNILA
Smoke Detectors 7/29/2024 Corrections Issued THOMAS FINNILA
Final 8/5/2024 Conditional Approval THOMAS FINNILA
Smoke Detectors 8/5/2024 Approved THOMAS FINNILA