14701 W KINGSBURY ST 91345

Certificate Information: 14701 W KINGSBURY ST 91345

Application / Permit
22010-20000-04684
Plan Check / Job No.
B22VN14181
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING (1443 SQFT) PER SB9 W/ATTACHED 2 CAR GARAGE (397 SQFT) W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/23/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 PETER MOSESIAN
Corrections Issued 10/8/2022 PETER MOSESIAN
Quality Review Completed 10/14/2022 OMID HEDAYAT
Building Plans Picked Up 10/14/2022 APPLICANT
Plan Check Approved 5/23/2023 PETER MOSESIAN
Issued 5/23/2023 APPLICANT
CofO in Progress 10/22/2024 JENNIFER RABUCHIN
CofO Issued 11/14/2024 DANIEL ORRANTE
Permit Finaled 11/14/2024 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 10/26/2022 NELSON RODRIGUEZ
Address approval Cleared 2/15/2023 COLIN LOREDO
Senate Bill 9 Cleared 2/17/2023 NELSON RODRIGUEZ
Hydrant and Access approval Cleared 4/8/2023 GILBERT URREA
Hydrant and Access approval Cleared 4/8/2023 GILBERT URREA
Low Impact Development Cleared 5/2/2023 ERNEST TSE
Eng Process Fee Ord 176,300 Cleared 5/3/2023 COLIN LOREDO
Sewer availability Cleared 5/4/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 5/9/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Van, Valkenburg, John; Lic. No.: C74939 13259 KISMET AVE      SYLMAR, CA 91342

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/3/2023 Corrections Issued JENNIFER RABUCHIN
METHANE-Subgrade 7/3/2023 Not Ready for Inspection JENNIFER RABUCHIN
Pre-Inspection 7/3/2023 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 7/24/2023 Partial Approval JENNIFER RABUCHIN
METHANE-Barrier 7/24/2023 Partial Approval JENNIFER RABUCHIN
METHANE-Subgrade 7/24/2023 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/4/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 8/4/2023 Corrections Issued JENNIFER RABUCHIN
Insulation 8/8/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 8/8/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 8/17/2023 Not Ready for Inspection ROBERT GOLD
METHANE-Barrier 8/17/2023 Not Ready for Inspection ROBERT GOLD
METHANE-Final 8/17/2023 Not Ready for Inspection ROBERT GOLD
METHANE-Subgrade 8/17/2023 Not Ready for Inspection ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 8/24/2023 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 8/24/2023 Approved JENNIFER RABUCHIN
METHANE-Barrier 8/24/2023 Approved JENNIFER RABUCHIN
METHANE-Final 8/24/2023 Approved JENNIFER RABUCHIN
METHANE-Subgrade 8/24/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/20/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/4/2023 Corrections Issued DAVID ANDERSON
Green Building Rough 12/4/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 12/4/2023 Approved DAVID ANDERSON
MERV13>=Rough 12/4/2023 Approved DAVID ANDERSON
Rough-Elec/Plmb/HVAC 12/4/2023 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 12/4/2023 Approved DAVID ANDERSON
ELECTRICAL-Rough 12/11/2023 Corrections Issued JENNIFER RABUCHIN
Insulation 12/11/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 1/10/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 1/10/2024 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 1/19/2024 Approved JENNIFER RABUCHIN
Shower Pan 1/19/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/22/2024 Partial Inspection JOHN COLEMAN
Final 5/22/2024 Corrections Issued JOHN COLEMAN
Green Building Final 5/22/2024 Corrections Issued JOHN COLEMAN
MERV13>=Final 5/22/2024 Corrections Issued JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 5/22/2024 SGSOV Not Required JOHN COLEMAN
Service/Power Release 5/22/2024 Not Ready for Inspection JOHN COLEMAN
Smoke Detectors 5/22/2024 Approved JOHN COLEMAN
BUILDING-Rough-Frame 8/1/2024 Approved JENNIFER RABUCHIN
Final 8/1/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 8/1/2024 Approved JENNIFER RABUCHIN
MERV13>=Final 8/1/2024 Approved JENNIFER RABUCHIN
Service/Power Release 8/1/2024 Not Ready for Inspection JENNIFER RABUCHIN
Final 8/23/2024 Corrections Issued JENNIFER RABUCHIN
Service/Power Release 8/23/2024 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 10/2/2024 Approved JENNIFER RABUCHIN
Final 10/2/2024 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 10/2/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/2/2024 Approved JENNIFER RABUCHIN
Service/Power Release 10/2/2024 Approved JENNIFER RABUCHIN