14701 W KINGSBURY ST 91345
Certificate Information: 14701 W KINGSBURY ST 91345
- Application / Permit
- 22010-20000-04684
- Plan Check / Job No.
- B22VN14181
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING (1443 SQFT) PER SB9 W/ATTACHED 2 CAR GARAGE (397 SQFT) W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/23/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | PETER MOSESIAN |
| Corrections Issued | 10/8/2022 | PETER MOSESIAN |
| Quality Review Completed | 10/14/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 10/14/2022 | APPLICANT |
| Plan Check Approved | 5/23/2023 | PETER MOSESIAN |
| Issued | 5/23/2023 | APPLICANT |
| CofO in Progress | 10/22/2024 | JENNIFER RABUCHIN |
| CofO Issued | 11/14/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/14/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 10/26/2022 | NELSON RODRIGUEZ |
| Address approval | Cleared | 2/15/2023 | COLIN LOREDO |
| Senate Bill 9 | Cleared | 2/17/2023 | NELSON RODRIGUEZ |
| Hydrant and Access approval | Cleared | 4/8/2023 | GILBERT URREA |
| Hydrant and Access approval | Cleared | 4/8/2023 | GILBERT URREA |
| Low Impact Development | Cleared | 5/2/2023 | ERNEST TSE |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 5/4/2023 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 5/9/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Van, Valkenburg, John; Lic. No.: C74939 | 13259 KISMET AVE SYLMAR, CA 91342 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/3/2023 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Subgrade | 7/3/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Pre-Inspection | 7/3/2023 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/24/2023 | Partial Approval | JENNIFER RABUCHIN |
| METHANE-Barrier | 7/24/2023 | Partial Approval | JENNIFER RABUCHIN |
| METHANE-Subgrade | 7/24/2023 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/4/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/4/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 8/8/2023 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/8/2023 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 8/17/2023 | Not Ready for Inspection | ROBERT GOLD |
| METHANE-Barrier | 8/17/2023 | Not Ready for Inspection | ROBERT GOLD |
| METHANE-Final | 8/17/2023 | Not Ready for Inspection | ROBERT GOLD |
| METHANE-Subgrade | 8/17/2023 | Not Ready for Inspection | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2023 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/24/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 8/24/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Final | 8/24/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 8/24/2023 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/4/2023 | Corrections Issued | DAVID ANDERSON |
| Green Building Rough | 12/4/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 12/4/2023 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 12/4/2023 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 12/4/2023 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 12/4/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 12/11/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 12/11/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 1/10/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/10/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/19/2024 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 1/19/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/22/2024 | Partial Inspection | JOHN COLEMAN |
| Final | 5/22/2024 | Corrections Issued | JOHN COLEMAN |
| Green Building Final | 5/22/2024 | Corrections Issued | JOHN COLEMAN |
| MERV13>=Final | 5/22/2024 | Corrections Issued | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 5/22/2024 | SGSOV Not Required | JOHN COLEMAN |
| Service/Power Release | 5/22/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Smoke Detectors | 5/22/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 8/1/2024 | Approved | JENNIFER RABUCHIN |
| Final | 8/1/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 8/1/2024 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 8/1/2024 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 8/1/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 8/23/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 8/23/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/2/2024 | Approved | JENNIFER RABUCHIN |
| Final | 10/2/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 10/2/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/2/2024 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 10/2/2024 | Approved | JENNIFER RABUCHIN |