12202 W HATTERAS ST 91607
Certificate Information: 12202 W HATTERAS ST 91607
- Application / Permit
- 22010-20000-04678
- Plan Check / Job No.
- B22VN14165
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 38' X 34' TWO STORY ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33 (C) AND (D) W/ATTACHED THREE-CAR GARAGE , ALL WORK PER ENGINEERING . “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 12/13/2022
- Issuing Office
- Current Status
- CofO Issued on 6/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2022 | RARES BODEA |
| Corrections Issued | 9/26/2022 | RARES BODEA |
| Quality Review Completed | 9/29/2022 | STEVEN KIM |
| Building Plans Picked Up | 9/30/2022 | APPLICANT |
| Applicant returned to address corrections | 12/8/2022 | RARES BODEA |
| Plan Check Approved | 12/13/2022 | RARES BODEA |
| Issued | 12/13/2022 | APPLICANT |
| CofO in Progress | 5/24/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 6/6/2024 | RUBEN SALAS |
| CofO Issued | 6/6/2024 | RUBEN SALAS |
| Permit Finaled | 6/6/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/13/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/13/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/13/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Conditional Approval | JOHN COLEMAN |
| PLUMBING-Rough | 12/16/2022 | Conditional Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Approved | KIRK SANDERS |
| Insulation | 12/19/2022 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2023 | Partial Approval | RYAN SALAZAR |
| Deputy Wood Construction | 2/10/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2023 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/3/2023 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2023 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 3/3/2023 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 3/22/2023 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 3/24/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 3/29/2023 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/10/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 4/10/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 4/10/2023 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 4/10/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/18/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 4/18/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 4/18/2023 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/18/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 5/12/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 5/12/2023 | Approved | KIRK SANDERS |
| Shower Pan | 5/12/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 5/24/2023 | Approved | KIRK SANDERS |
| Sewer | 6/6/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 6/27/2023 | Partial Approval | ROBERT GOLD |
| Underground Mechanical | 7/7/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 10/11/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 10/16/2023 | Corrections Issued | KIRK SANDERS |
| Grounding or Bonding | 10/16/2023 | Approved | KIRK SANDERS |
| HVAC-Final | 10/16/2023 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 10/24/2023 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 10/24/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 10/24/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 11/7/2023 | Conditional Approval | JUAN VALENZUELA |
| Gas Test | 11/7/2023 | Approved | JUAN VALENZUELA |
| HVAC-Final | 11/7/2023 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 11/7/2023 | Approved | JUAN VALENZUELA |
| Final | 4/23/2024 | No Access for Inspection | JOSE AVILA |
| Final | 5/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 5/10/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 5/10/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 5/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 5/15/2024 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 5/15/2024 | Approved | JUAN VALENZUELA |
| Service/Power Release | 5/15/2024 | Partial Inspection | JUAN VALENZUELA |
| Smoke Detectors | 5/15/2024 | Approved | JUAN VALENZUELA |
| Pre-Inspection | 5/21/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Service/Power Release | 5/21/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 5/23/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Service/Power Release | 5/23/2024 | Approved | OGANES TARAKHCHYAN |