13864 W FOOTHILL BLVD 91342
Certificate Information: 13864 W FOOTHILL BLVD 91342
- Application / Permit
- 22010-20000-04677
- Plan Check / Job No.
- B22VN14158
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- Eplan. Trash enclosure stand alone for In-N-Out Burger restaurant.
- Permit Issued
- Issued on 7/27/2023
- Issuing Office
- Current Status
- Permit Finaled on 7/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | HELEN NGUYEN |
| Corrections Issued | 10/7/2022 | HELEN NGUYEN |
| Quality Review Completed | 11/4/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 1/26/2023 | HELEN NGUYEN |
| Applicant returned to address corrections | 3/16/2023 | HELEN NGUYEN |
| Plan Check Approved | 4/28/2023 | HELEN NGUYEN |
| Issued | 7/27/2023 | APPLICANT |
| Permit Finaled | 7/14/2025 | ROBERT DAVIS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2022 | LEE GUILBEAUX |
| APC | Cleared | 1/3/2023 | ANACANY HURTADO |
| Community Plan Implem. Overlay | Cleared | 1/3/2023 | ANACANY HURTADO |
| ZA Case | Cleared | 1/3/2023 | ANACANY HURTADO |
| ZA Case | Cleared | 1/3/2023 | ANACANY HURTADO |
| ZA Case | Cleared | 1/3/2023 | ANACANY HURTADO |
| Roof/Waste drainage to street | Cleared | 4/24/2023 | LEE GUILBEAUX |
Contact Information
| Architect | , ; Lic. No.: C40152 | 17205 W 94TH AVE ARVADA, CO 80007 |
| Contractor | In-N-Out Burgers; Lic. No.: 470763-B | , |
| Engineer | Lamoureux,, Mark; Lic. No.: C38382 | 426 SAGE PLACE GLENDORA, CA 91740 |
| Engineer | Roberts,, Ronald Andrew; Lic. No.: C41650 | 2948 N STEMMONS FREEWAY DALLAS, TX 752476103 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Reinforced Masonry Frame | 11/1/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 11/6/2023 | Partial Approval | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 1/23/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 1/25/2024 | Partial Approval | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 1/25/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 1/25/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Interior/Exterior Lathing | 2/15/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Interior/Exterior Lathing | 6/24/2024 | Approved | DANNY RODRIGUEZ |
| Final | 7/14/2025 | Permit Finaled | ROBERT DAVIS |
| Footing/Foundation/Slab | 7/14/2025 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 7/14/2025 | SGSOV No Gas | ROBERT DAVIS |
| Smoke Detectors | 7/14/2025 | Approved | ROBERT DAVIS |
| Verify Sprinkler Sign Off | 7/14/2025 | Approved | ROBERT DAVIS |
| Wood Frame | 7/14/2025 | Approved | ROBERT DAVIS |