10246 N SCOVILLE AVE 91040
Certificate Information: 10246 N SCOVILLE AVE 91040
- Application / Permit
- 22010-20000-04650
- Plan Check / Job No.
- B22VN14041
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan new detached ADU (800 sq.ft.) per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)(d) and (g)
- Permit Issued
- Issued on 7/28/2023
- Issuing Office
- Current Status
- CofO Issued on 8/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | NGHI SU |
| Corrections Issued | 10/7/2022 | NGHI SU |
| Quality Review Completed | 10/14/2022 | FARUK SEZER |
| Applicant returned to address corrections | 3/16/2023 | NGHI SU |
| Plan Check Approved | 3/23/2023 | NGHI SU |
| Issued | 7/28/2023 | APPLICANT |
| CofO in Progress | 8/8/2024 | DAVID ANDERSON |
| Permit Finaled | 8/20/2024 | DANIEL ORRANTE |
| CofO Issued | 8/20/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/20/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/12/2022 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2022 | FERNANDO GIL |
| Sewer availability | Cleared | 10/13/2022 | FERNANDO GIL |
| Grading Pre-Inspection | Cleared | 10/18/2022 | KIRK LINKLATER |
| Low Impact Development | Cleared | 12/20/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 12/21/2022 | FERNANDO GIL |
| Construction near power lines | Cleared | 1/8/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/8/2023 | RIDWAN HARDY |
| SB8 RUD | Cleared | 1/12/2023 | NICHOLAS KAWAZOE |
| GPI Written Notices | Cleared | 3/16/2023 | NGHI SU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Karapetian,, Arbi; Lic. No.: C79953 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/15/2023 | Partial Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 12/20/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 2/12/2024 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 2/12/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 2/12/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 2/12/2024 | Approved | DAVID ANDERSON |
| Wood Frame | 2/12/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 2/14/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 2/14/2024 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 2/14/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 2/23/2024 | Partial Approval | DAVID ANDERSON |
| Shower Pan | 2/23/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Insulation | 2/28/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 2/28/2024 | Approved | WILLIAM WREN |
| Shower Pan | 2/28/2024 | Approved | WILLIAM WREN |
| Drywall Nailing | 3/6/2024 | Approved | DAVID ANDERSON |
| Gas Test | 5/3/2024 | Approved | DAVID ANDERSON |
| Underground Mechanical | 5/3/2024 | Approved | DAVID ANDERSON |
| Final | 7/17/2024 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 7/17/2024 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 7/17/2024 | SGSOV Not Ready | DAVID ANDERSON |
| Service/Power Release | 7/17/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 7/17/2024 | Approved | DAVID ANDERSON |
| Final | 8/7/2024 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 8/7/2024 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 8/7/2024 | Approved | DAVID ANDERSON |