631 1/2 E 80TH ST 90001
Certificate Information: 631 1/2 E 80TH ST 90001
- Application / Permit
- 22010-20000-04633
- Plan Check / Job No.
- B22VN13990
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **EPLAN** Convert existing detached garage to Accessory Dwelling Unit . And addition to rear for 2nd Accessory Dwelling Unit . WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS. **Only (1) Accessory Dwelling Unit is allowed when accessory to a Single Family Dwelling** "COMPLY WITH DEPARTMENT ORDER effective date 08/26/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS #966472.
- Permit Issued
- Issued on 3/28/2023
- Issuing Office
- Current Status
- CofO Issued on 6/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2022 | GEORGE ALVAREZ |
| Corrections Issued | 10/11/2022 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 1/14/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 3/22/2023 | LAWRENCE QUIRANTE |
| Plan Check Approved | 3/27/2023 | JOSEPH RAFOLS |
| Issued | 3/28/2023 | APPLICANT |
| CofO in Progress | 5/27/2025 | DANIEL GONZALEZ |
| Permit Finaled | 6/25/2025 | CLAUDIO MORENO |
| CofO Issued | 6/25/2025 | CLAUDIO MORENO |
| Permit Finaled | 6/25/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/9/2022 | TREVOR QUAN |
| Address approval | Cleared | 12/14/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 1/6/2023 | TREVOR QUAN |
| Construction near power lines | Cleared | 3/17/2023 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/11/2023 | Approved | MARIO CUEVAS |
| Footing/Foundation/Slab | 5/4/2023 | Corrections Issued | DANIEL GUEVARA |
| Footing/Foundation/Slab | 6/16/2023 | Approved | DANIEL GUEVARA |
| Rough-Elec/Plmb/HVAC | 7/17/2023 | Partial Approval | DANIEL GUEVARA |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Approved | DANIEL GUEVARA |
| Rough-Elec/Plmb/HVAC | 7/18/2023 | Not Ready for Inspection | DANIEL GUEVARA |
| Wood Frame | 7/18/2023 | Partial Approval | DANIEL GUEVARA |
| Rough-Elec/Plmb/HVAC | 8/3/2023 | Approved | DANIEL GUEVARA |
| Insulation | 8/17/2023 | Approved | DANIEL GUEVARA |
| Drywall Nailing | 8/28/2023 | Approved | DANIEL GUEVARA |
| Interior/Exterior Lathing | 8/29/2023 | Approved | DANIEL GUEVARA |
| Shower Pan | 8/29/2023 | Approved | DANIEL GUEVARA |
| BUILDING-Rough-Frame | 10/18/2023 | Approved | DANIEL GUEVARA |
| ELECTRICAL-Final | 10/18/2023 | Approved | DANIEL GUEVARA |
| HVAC-Final | 10/18/2023 | Approved | DANIEL GUEVARA |
| PLUMBING-Final | 10/18/2023 | Approved | DANIEL GUEVARA |
| Final | 10/31/2023 | Conditional Approval | DANIEL GUEVARA |
| SGSOV-Seismic Gas S/O Valve | 10/31/2023 | SGSOV Approved | DANIEL GUEVARA |
| Smoke Detectors | 10/31/2023 | Approved | DANIEL GUEVARA |
| Final | 5/27/2025 | OK to Issue CofO | DANIEL GONZALEZ |