207-209 W 49TH ST 90037
Certificate Information: 207-209 W 49TH ST 90037
- Application / Permit
- 22010-20000-04623
- Plan Check / Job No.
- B22VN13951
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Eplan NEW 90'6" X 25' 2-STORY DUPLEX & ATTACHED (1)-CAR GARAGE , (2) CAR GARAGE AND ( 1 ) CAR CARPORT, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 2/28/2023
- Issuing Office
- Current Status
- CofO Issued on 8/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2022 | RARES BODEA |
| Corrections Issued | 9/29/2022 | RARES BODEA |
| Quality Review Completed | 10/5/2022 | STEVEN KIM |
| Plan Check Approved | 12/20/2022 | RARES BODEA |
| Issued | 2/28/2023 | APPLICANT |
| CofO in Progress | 8/10/2023 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 8/21/2023 | DEROLD HAUFF |
| CofO Issued | 8/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Highway dedication | Cleared | 10/12/2022 | WALLIE JONG |
| Address approval | Cleared | 10/13/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2022 | THAN WIN |
| Sewer availability | Cleared | 10/21/2022 | WALLIE JONG |
| Frnt yard landscape/Water mgmt | Cleared | 11/3/2022 | DALIA MOKAYED |
| Hydrant and Access approval | Cleared | 11/4/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 11/29/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 11/30/2022 | WALLIE JONG |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/5/2023 | Approved | BRENDAN MORELLI |
| Footing/Foundation/Slab | 4/5/2023 | Approved | BRENDAN MORELLI |
| Deputy Reinf. Concrete | 4/6/2023 | Conditional Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 4/14/2023 | Partial Approval | BRENDAN MORELLI |
| Sewer | 4/14/2023 | Partial Approval | BRENDAN MORELLI |
| Wood Frame | 4/14/2023 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2023 | Partial Approval | BRENDAN MORELLI |
| Insulation | 4/17/2023 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2023 | Partial Approval | BRENDAN MORELLI |
| Deputy Wood Construction | 5/10/2023 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | No Access for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 5/25/2023 | Corrections Issued | STUART CHAPMAN |
| HVAC-Rough | 5/25/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 5/25/2023 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/26/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/26/2023 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 5/26/2023 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 5/26/2023 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 6/8/2023 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 6/8/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 6/16/2023 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 6/20/2023 | Partial Approval | BRENDAN MORELLI |
| Interior/Exterior Lathing | 6/30/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/3/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/28/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/8/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/8/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/8/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 8/8/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/8/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/8/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/8/2023 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/8/2023 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/8/2023 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/8/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/9/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/9/2023 | Approved | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 8/11/2023 | Partial Inspection | SCOTT FINNILA |
| Service/Power Release | 8/14/2023 | Approved | ALEJANDRO DE ARTOLA |