20410 W PARTHENIA ST 91306

Certificate Information: 20410 W PARTHENIA ST 91306

Application / Permit
22010-20000-04617
Plan Check / Job No.
B22VN13936
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN PROPOSED ONE STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g
Permit Issued
Issued on 6/24/2023
Issuing Office
Current Status
CofO Issued on 4/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2022 APPLICANT
Assigned to Plan Check Engineer 9/21/2022 JOSEPH RAFOLS
Corrections Issued 9/22/2022 JOSEPH RAFOLS
Plan Check Approved 6/23/2023 MICHAEL LOPEZ
Issued 6/24/2023 APPLICANT
CofO in Progress 4/18/2025 JEFFREY HARTLINE
Permit Finaled 4/28/2025 JOHN JANSON
CofO Issued 4/28/2025 JOHN JANSON
Permit Finaled 4/28/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/22/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/26/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 10/30/2022 JOHN CONNEALLY
Low Impact Development Cleared 2/8/2023 MITESH PATEL
Roof/Waste drainage to street Cleared 5/16/2023 CARLOS AGUILERA
Private sewage disp. approval Cleared 6/1/2023 DAN RYAN EVANGELISTA

Contact Information

Contractor Markarian Setrag; Lic. No.: 832632-B       ,
Contractor Pampa Investment Inc; Lic. No.: 832632-B       ,
Engineer Moser,, Bradley Charles; Lic. No.: C68803 116 OAKSIDE LN      BUELLTON, CA 93427

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/11/2023 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 11/8/2023 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 11/27/2023 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 11/27/2023 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 12/4/2023 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 12/21/2023 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/5/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/5/2024 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 1/5/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 1/5/2024 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 1/24/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 2/6/2024 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Rough 3/7/2024 Approved JEFFREY HARTLINE
Underground Mechanical 3/13/2024 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 3/28/2024 Approved JEFFREY HARTLINE
Green Building Rough 3/28/2024 Approved JEFFREY HARTLINE
HVAC-Rough 3/28/2024 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 3/28/2024 Approved JEFFREY HARTLINE
Insulation 4/25/2024 Approved JEFFREY HARTLINE
Drywall Nailing 5/2/2024 Approved JEFFREY HARTLINE
Shower Pan 5/2/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 5/14/2024 Partial Approval JEFFREY HARTLINE
HVAC-Final 8/23/2024 Not Ready for Inspection JEFFREY HARTLINE
PLUMBING-Rough 9/19/2024 Not Ready for Inspection JEFFREY HARTLINE
PLUMBING-Final 9/27/2024 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 2/19/2025 Partial Approval JOHN COLEMAN
ELECTRICAL-Final 4/11/2025 Approved CHRIS CHRISTENSEN
Final 4/11/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 4/11/2025 Approved CHRIS CHRISTENSEN
HVAC-Final 4/11/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Final 4/11/2025 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/11/2025 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 4/11/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Smoke Detectors 4/11/2025 Approved CHRIS CHRISTENSEN
Final 4/18/2025 OK to Issue CofO JEFFREY HARTLINE
Service/Power Release 4/18/2025 Approved JEFFREY HARTLINE