2806 S BENTLEY AVE 90064

Certificate Information: 2806 S BENTLEY AVE 90064

Application / Permit
22010-20000-04611
Plan Check / Job No.
B22VN13929
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 18'-6" X 35' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 2/21/2023
Issuing Office
Valley
Current Status
CofO in Progress on 5/29/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/15/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 SELLA BENYAMIN
Corrections Issued 10/13/2022 SELLA BENYAMIN
Quality Review Completed 10/19/2022 STEVEN KIM
Building Plans Picked Up 10/20/2022 APPLICANT
Plan Check Approved 2/10/2023 SELLA BENYAMIN
Issued 2/21/2023 APPLICANT
CofO in Progress 5/29/2026 KIRK SANDERS

Permit Application Clearance Information

Address approval Cleared 11/10/2022 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 1/9/2023 DINAH GARIN
Sewer availability Cleared 1/9/2023 DINAH GARIN
Low Impact Development Cleared 1/30/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 1/31/2023 ANTHONY MAINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Pezeshkian,, Vahik; Lic. No.: C35278 1545 N VERDUGO RD 217      GLENDALE, CA 91208

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/11/2023 Corrections Issued JOHNNY MIRANDA
Underground Mechanical 5/12/2023 Partial Approval JOHNNY MIRANDA
Reinforced Concrete Frame 5/24/2023 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Corrections Issued JESUS PINEDA
Green Building Rough 9/12/2023 Not Ready for Inspection JESUS PINEDA
MERV13>=Rough 9/12/2023 Approved JESUS PINEDA
Rough-Elec/Plmb/HVAC 9/12/2023 Not Ready for Inspection JESUS PINEDA
Verify Sprinkler Sign Off 9/12/2023 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Rough 9/20/2023 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 9/20/2023 Approved JESUS PINEDA
HVAC-Rough 9/20/2023 Approved JESUS PINEDA
PLUMBING-Rough 9/20/2023 Approved JESUS PINEDA
Sewer 9/20/2023 Approved JESUS PINEDA
Underground Mechanical 9/20/2023 Approved JESUS PINEDA
Deputy Wood Construction 9/21/2023 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 10/18/2023 Corrections Issued CLAYTON GRAHAM
Green Building Rough 10/18/2023 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 10/18/2023 Partial Approval CLAYTON GRAHAM
Underground Mechanical 10/18/2023 Partial Approval CLAYTON GRAHAM
BUILDING-Rough-Frame 10/25/2023 Approved JESUS PINEDA
Insulation 10/31/2023 Corrections Issued BEN MOLSTAD
Insulation 11/27/2023 Approved JESUS PINEDA
Drywall Nailing 12/5/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 1/23/2024 Corrections Issued KATHRYN BUTTERWORTH
Shower Pan 1/23/2024 Corrections Issued KATHRYN BUTTERWORTH
Interior/Exterior Lathing 1/25/2024 Partial Approval KATHRYN BUTTERWORTH
Shower Pan 1/25/2024 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 6/13/2024 Corrections Issued JESUS PINEDA
Final 6/13/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 6/13/2024 Approved JESUS PINEDA
Green Building Final 6/13/2024 Corrections Issued JESUS PINEDA
HVAC-Final 6/13/2024 Approved JESUS PINEDA
MERV13>=Final 6/13/2024 Approved JESUS PINEDA
PLUMBING-Final 6/13/2024 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 6/13/2024 SGSOV Approved JESUS PINEDA
Service/Power Release 6/13/2024 Not Ready for Inspection JESUS PINEDA
Smoke Detectors 6/13/2024 Approved JESUS PINEDA
Final 2/11/2025 Not Ready for Inspection DANIEL VERA
Green Building Final 2/11/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Final 2/11/2025 Approved DANIEL VERA
Service/Power Release 2/11/2025 Not Ready for Inspection DANIEL VERA
Final 3/14/2025 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 5/28/2025 Corrections Issued WILBER ROSALES
Final 6/13/2025 Corrections Issued BOBBY KEY
Green Building Final 6/13/2025 Approved BOBBY KEY
Service/Power Release 6/13/2025 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 5/6/2026 Approved EUGENE CASSIDY
Final 5/6/2026 Corrections Issued EUGENE CASSIDY
Service/Power Release 5/6/2026 Not Required EUGENE CASSIDY
Final 5/28/2026 OK to Issue CofO KIRK SANDERS