19546 W HART ST 91335
Certificate Information: 19546 W HART ST 91335
- Application / Permit
- 22010-20000-04564
- Plan Check / Job No.
- B22VN13756
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 20'-2" X 27' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 4/30/2023
- Issuing Office
- Current Status
- CofO Issued on 8/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2022 | ALEC MOUSAKHANIAN |
| Corrections Issued | 9/23/2022 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 3/22/2023 | ALEC MOUSAKHANIAN |
| Issued | 4/30/2023 | APPLICANT |
| CofO in Progress | 7/9/2024 | JEFFREY BULL |
| Permit Finaled | 8/6/2024 | JOHN JANSON |
| CofO Issued | 8/6/2024 | JOHN JANSON |
| Permit Finaled | 8/6/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/7/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 11/15/2022 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 12/3/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/3/2022 | RIDWAN HARDY |
| Miscellaneous | Cleared | 12/14/2022 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2023 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 3/13/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 3/15/2023 | ROMAN GUTIERREZ |
| Hold | Cleared | 5/11/2023 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/24/2023 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 8/31/2023 | Approved | JEFFREY BULL |
| Reinforced Concrete Frame | 8/31/2023 | Approved | JEFFREY BULL |
| Reinforced Masonry Frame | 8/31/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 10/4/2023 | Not Ready for Inspection | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 10/26/2023 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 10/26/2023 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Rough | 10/26/2023 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Rough | 10/26/2023 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 10/26/2023 | Approved | JEFFREY BULL |
| Verify Sprinkler Sign Off | 10/26/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 11/1/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 11/1/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 11/1/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 11/1/2023 | Approved | JEFFREY BULL |
| Insulation | 11/7/2023 | Approved | MORRIS JACKSON |
| Drywall Nailing | 11/9/2023 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 12/4/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 1/10/2024 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Final | 1/10/2024 | Approved | JEFFREY BULL |
| Service/Power Release | 1/10/2024 | Approved | JEFFREY BULL |
| Final | 2/7/2024 | Corrections Issued | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2024 | Approved | JEFFREY BULL |
| Green Building Final | 2/7/2024 | Not Ready for Inspection | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 2/7/2024 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 2/7/2024 | Approved | JEFFREY BULL |
| Final | 6/26/2024 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Final | 6/26/2024 | Approved | JEFFREY BULL |
| Final | 7/9/2024 | OK to Issue CofO | JEFFREY BULL |