10326 N QUILL AVE 91040
Certificate Information: 10326 N QUILL AVE 91040
- Application / Permit
- 22010-20000-04559
- Plan Check / Job No.
- B22VN13721
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ONE STORY 35'-7" X 25'-10" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING SEE COMMENTS
- Permit Issued
- Issued on 4/6/2023
- Issuing Office
- Current Status
- CofO Issued on 3/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 10/14/2022 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 10/21/2022 | OMID HEDAYAT |
| Applicant returned to address corrections | 3/11/2023 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 4/1/2023 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 4/4/2023 | SEWADA ZADOORAN MILAGARDI |
| Issued | 4/6/2023 | APPLICANT |
| CofO in Progress | 2/8/2024 | DAVID ANDERSON |
| Permit Finaled | 3/4/2024 | RUBEN SALAS |
| CofO Issued | 3/4/2024 | RUBEN SALAS |
| Permit Finaled | 3/4/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2022 | MEGAN GODINEZ |
| Grading Pre-Inspection | Cleared | 11/23/2022 | KIRK LINKLATER |
| Sewer availability | Cleared | 11/28/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2022 | ROSE MARIE SMITH |
| Construction near power lines | Cleared | 1/28/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/28/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/3/2023 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/21/2023 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 4/3/2023 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng D; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/2/2023 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 5/2/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Grading Pre-Inspection | 5/2/2023 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 5/2/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Pre-Inspection | 5/2/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 5/9/2023 | Partial Approval | DAVID ANDERSON |
| Pre-Inspection | 5/9/2023 | Approved | DAVID ANDERSON |
| Sewer | 5/9/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 5/15/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Partial Approval | DAVID ANDERSON |
| Special/Order Compliance | 6/12/2023 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 7/12/2023 | Corrections Issued | DAVID ANDERSON |
| HVAC-Rough | 7/12/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 7/12/2023 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 7/25/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 7/25/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/25/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 7/25/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 8/15/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 8/15/2023 | Approved | DAVID ANDERSON |
| Insulation | 8/15/2023 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 8/15/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 9/7/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 10/17/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 10/19/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 10/19/2023 | Partial Approval | DAVID ANDERSON |
| Sewer | 10/20/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 10/20/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 12/6/2023 | Corrections Issued | DAVID ANDERSON |
| HVAC-Final | 12/6/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Final | 12/13/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 12/13/2023 | Approved | DAVID ANDERSON |
| Final | 1/18/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 1/18/2024 | Approved | DAVID ANDERSON |
| Green Building Final | 1/18/2024 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 1/18/2024 | SGSOV Not Ready | DAVID ANDERSON |
| Service/Power Release | 1/18/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 1/18/2024 | Approved | DAVID ANDERSON |
| Final | 1/25/2024 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 1/25/2024 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 1/25/2024 | Approved | DAVID ANDERSON |