18946 W SATICOY ST 91335

Certificate Information: 18946 W SATICOY ST 91335

Application / Permit
22010-20000-04547
Plan Check / Job No.
B22VN13684
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX 20'7" x 20'7" GARAGE AND ADD 14'7" x 29'10" (IRR. SHAPE) FOR ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c)-(d) PER ENGINEERING
Permit Issued
Issued on 1/11/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2022 APPLICANT
Assigned to Plan Check Engineer 9/13/2022 JEFFREY TANGONAN
Corrections Issued 9/14/2022 JEFFREY TANGONAN
Building Plans Picked Up 9/15/2022 APPLICANT
Plan Check Approved 12/7/2022 ALFRED RAMIREZ
Issued 1/11/2023 APPLICANT
CofO in Progress 8/21/2023 JEFFREY BULL
Permit Finaled 9/5/2023 JOHN JANSON
CofO Issued 9/5/2023 JOHN JANSON
Permit Finaled 9/5/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/15/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 9/15/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 9/20/2022 ROMAN GUTIERREZ
Sewer availability Cleared 9/20/2022 ROMAN GUTIERREZ
Construction near power lines Cleared 12/1/2022 RIDWAN HARDY

Contact Information

Contractor Lifetime Home Builders Inc; Lic. No.: 1050605-B 1545 NORTH VERDUGO RD STE 232      GLENDALE, CA 91208
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/30/2023 Partial Approval JEFFREY BULL
Sewer 1/30/2023 Approved JEFFREY BULL
Underground Mechanical 2/13/2023 Approved MORRIS JACKSON
Deputy Drilled-In Anchors 2/16/2023 Conditional Approval JEFFREY BULL
Excavation/Setback/Form/Re-Bar 2/17/2023 Corrections Issued JON MCHUGH
Footing/Foundation/Slab 2/17/2023 Not Ready for Inspection JON MCHUGH
Excavation/Setback/Form/Re-Bar 2/22/2023 Approved JEFFREY BULL
Excavation/Setback/Form/Re-Bar 2/27/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Partial Approval JEFFREY BULL
ELECTRICAL-Rough 3/23/2023 No Access for Inspection SEAN HAUPT
PLUMBING-Rough 3/23/2023 No Access for Inspection SEAN HAUPT
ELECTRICAL-Rough 3/24/2023 Approved VINCENT HANLEY
PLUMBING-Rough 3/24/2023 Approved VINCENT HANLEY
Insulation 4/4/2023 Partial Approval JEFFREY BULL
Special/Order Compliance 4/4/2023 Partial Inspection MORRIS JACKSON
Wood Frame 4/4/2023 Not Ready for Inspection JEFFREY BULL
Deputy Wood Construction 4/6/2023 Conditional Approval JEFFREY BULL
Insulation 4/11/2023 Not Ready for Inspection JEFFREY BULL
Interior/Exterior Lathing 4/11/2023 Partial Approval JEFFREY BULL
Drywall Nailing 4/19/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 5/11/2023 Approved JUSTIN HAWLEY
Shower Pan 5/11/2023 Partial Approval JUSTIN HAWLEY
Shower Pan 5/15/2023 Approved JEFFREY BULL
Service/Power Release 7/5/2023 Not Ready for Inspection SEAN WIRCH
Underground Mechanical 7/24/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 8/14/2023 Approved JEFFREY BULL
Final 8/14/2023 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 8/14/2023 Approved JEFFREY BULL
Green Building Final 8/14/2023 Not Ready for Inspection JEFFREY BULL
Green Building Rough 8/14/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 8/14/2023 SGSOV Not Ready JEFFREY BULL
Smoke Detectors 8/14/2023 Approved JEFFREY BULL
ELECTRICAL-Final 8/18/2023 Approved JEFFREY BULL
Final 8/18/2023 OK to Issue CofO JEFFREY BULL
Green Building Final 8/18/2023 Approved JEFFREY BULL
HVAC-Final 8/18/2023 Approved JEFFREY BULL
PLUMBING-Final 8/18/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 8/18/2023 SGSOV Approved JEFFREY BULL
Service/Power Release 8/18/2023 Not Required JEFFREY BULL