10729 N FULLBRIGHT AVE 91311
Certificate Information: 10729 N FULLBRIGHT AVE 91311
- Application / Permit
- 22010-20000-04528
- Plan Check / Job No.
- B22VN13626
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 38'-8" X 15'-4" IRREGULAR SHAPED FULLY SPRINKLERED ACCESSORY DWELLING UNIT (482 SQ FT) PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g)
- Permit Issued
- Issued on 11/16/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 9/12/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 9/16/2022 | APPLICANT |
| Plan Check Approved | 11/3/2022 | JEROME MAGAT PALMA |
| Issued | 11/16/2022 | APPLICANT |
| CofO in Progress | 8/3/2023 | DAVID SCANTLIN |
| Permit Finaled | 8/4/2023 | JOHN JANSON |
| CofO Issued | 8/4/2023 | JOHN JANSON |
| Permit Finaled | 8/4/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/30/2022 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 10/12/2022 | KIRK LINKLATER |
| Hydrant and Access approval | Cleared | 10/25/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 10/27/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 10/27/2022 | DAGOVERTO GUERRERO |
| GPI Written Notices | Cleared | 11/3/2022 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Nork Construction Inc; Lic. No.: 1058592-B | 17204 CHATSWORTH ST #10 GRANADA HILLS, CA 91344 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/7/2022 | Not Ready for Inspection | JOHN KIDWELL |
| Underground Mechanical | 12/13/2022 | Approved | KRISTEN CAUSEY |
| Excavation/Setback/Form/Re-Bar | 12/22/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 12/22/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/28/2023 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 3/28/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 3/28/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Rough | 3/28/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 3/28/2023 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 3/28/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 4/5/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 4/5/2023 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 4/5/2023 | Partial Approval | DAVID SCANTLIN |
| Drywall Nailing | 4/17/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Insulation | 4/17/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Special/Order Compliance | 4/17/2023 | Partial Inspection | MORRIS JACKSON |
| Shower Pan | 5/11/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 5/25/2023 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 8/1/2023 | Approved | DAVID SCANTLIN |
| Final | 8/1/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 8/1/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 8/1/2023 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 8/1/2023 | Approved | DAVID SCANTLIN |
| Smoke Detectors | 8/1/2023 | Approved | DAVID SCANTLIN |
| Final | 8/3/2023 | OK to Issue CofO | DAVID SCANTLIN |