12149 N BAMBI PL 91344
Certificate Information: 12149 N BAMBI PL 91344
- Application / Permit
- 22010-20000-04527
- Plan Check / Job No.
- B22VN13623
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 23'-4" X 34'-3" FULLY SPRINKLERED DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g). <NFPA-13D SPRINKLER SYSTEM REQ'D>
- Permit Issued
- Issued on 6/26/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 9/13/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 9/15/2022 | APPLICANT |
| Applicant returned to address corrections | 4/24/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 6/23/2023 | HAYATO TSUCHIYA |
| Issued | 6/26/2023 | APPLICANT |
| CofO in Progress | 11/18/2025 | STEVEN BACK |
| Permit Finaled | 12/9/2025 | JOHN JANSON |
| CofO Issued | 12/9/2025 | JOHN JANSON |
| Permit Finaled | 12/9/2025 | JOHN JANSON |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 9/13/2022 | ARTIN ZARUKIAN |
| Grading Pre-Inspection | Cleared | 9/13/2022 | ARTIN ZARUKIAN |
| Address approval | Cleared | 2/22/2023 | MEGAN GODINEZ |
| Street Frontage | Cleared | 2/22/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 2/27/2023 | MEGAN GODINEZ |
| Hydrant and Access approval | Cleared | 4/14/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 6/21/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 6/22/2023 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 450 NORTH BRAND BLVD STE 600 GLENDALE, CA 91203 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/3/2023 | Corrections Issued | STEVEN BACK |
| Pre-Inspection | 12/2/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 12/6/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 12/23/2024 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 1/10/2025 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 2/5/2025 | No Access for Inspection | SCOTT SOBEL |
| Insulation | 2/10/2025 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 2/10/2025 | Partial Approval | JEFFREY PARD |
| Footing/Foundation/Slab | 2/18/2025 | Corrections Issued | STEVEN BACK |
| Insulation | 2/18/2025 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 2/24/2025 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2025 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 4/18/2025 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 4/18/2025 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 4/18/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 4/18/2025 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/18/2025 | Approved | CHRIS CHRISTENSEN |
| Sewer | 4/18/2025 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 4/18/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 4/18/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/24/2025 | Not Ready for Inspection | STEVEN BACK |
| Green Building Rough | 4/24/2025 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 4/28/2025 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 4/28/2025 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 4/28/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 5/2/2025 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 5/7/2025 | Approved | STEVEN BACK |
| Final | 5/7/2025 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 5/28/2025 | Approved | STEVEN BACK |
| Shower Pan | 5/28/2025 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 9/2/2025 | SGSOV Not Ready | JEFFREY PARD |
| Final | 9/8/2025 | Corrections Issued | STEVEN BACK |
| Green Building Final | 9/8/2025 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 9/8/2025 | SGSOV Not Required | STEVEN BACK |
| Service/Power Release | 9/8/2025 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 9/8/2025 | Approved | STEVEN BACK |
| Final | 10/23/2025 | No Access for Inspection | STEVEN BACK |
| Green Building Final | 10/23/2025 | No Access for Inspection | STEVEN BACK |
| Service/Power Release | 10/23/2025 | No Access for Inspection | STEVEN BACK |
| Final | 11/5/2025 | Not Ready for Inspection | STEVEN BACK |
| Green Building Final | 11/5/2025 | Approved | STEVEN BACK |
| Service/Power Release | 11/5/2025 | Not Required | STEVEN BACK |
| Final | 11/18/2025 | OK to Issue CofO | STEVEN BACK |
| Service/Power Release | 11/18/2025 | Approved | STEVEN BACK |